8. Slide the server in the rack.
9. If removed, install the bezel.
The installation is complete.
To configure arrays, see the HPE Smart Array SR Gen10 Configuration Guide at the
Installing a uFF drive and SCM drive carrier
For the supported drive bays, see
Procedure
1. If needed, install the uFF drive into the drive carrier.
2. To install a drive in outer drive cage, remove the bezel If installed.
3. To install a drive in inner drive cage, do the following:
NOTE: If the HPE designated cable management arm is not installed on the rack, ensure that the cables at the rear of
the server are not damaged while extending the server.
a. Extend the server from the rack.
b. To open the inner drive cage, press the cage latches.
The drive cage pops out of the chassis in the slanting position.
Hardware options installation
69
Summary of Contents for ProLiant DL325 Gen10 Plus
Page 36: ...10 Remove the inner drive cage blank 11 Remove the fan wall covers 36 Operations...
Page 37: ...12 For SFF drive cage remove the cable covers 13 Remove the drive cage latches Operations 37...
Page 38: ...14 Remove the outer drive cage LFF SFF 38 Operations...
Page 52: ...52 Operations...
Page 67: ...3 Remove the drive blank LFF SFF 4 Prepare the drive LFF Hardware options installation 67...
Page 119: ...SFF Cable routing Front I O LFF Cabling 119...
Page 120: ...SFF Cable routing Serial port 120 Cabling...