Installing and Configuring the Director
51
Director 2/140 Installation Guide
Note:
To ensure redundancy, install an second optional PDU and connect each PDU
power cord to a separate PDU. Also note that the Director 2/140 does not have a
power switch. Therefore, the Director 2/140 powers on when its power cords are
connected to facility power.
Figure 13: AC power connections (director)
Power-On Self Test
Use the following steps to run a Power-On Self Test (POST):
1. Power on the PDUs (if used).
The director powers on. The following occurs during POST:
■
Amber LEDs on both CTP cards and all universal port module (UPM)
cards illuminate momentarily.
■
The green LED on each CTP card (active and backup) turns O
N
as the
card is tested and UPM cards are tested.
■
Green LEDs associated with Fibre Channel ports sequentially illuminate
as the ports are tested.