Installing and Configuring the Director
44
Director 2/140 Installation Guide
WARNING:
Two people will need to work together to transfer the director to
the lift. Make sure the wheels of the lift cannot roll as you transfer the director
to the lift. Move the director slowly and carefully onto the lift to prevent back
and hand injury. Dropping the director could injure personnel or damage the
equipment.
1. Position the lift device next to the director.
2. Using a pallet jack, raise the pallet on which the director is mounted to the
same height as the top surface of the lift device.
3. Slide the director across from the pallet to the lift device.
4. Determine the appropriate rack-mount position. Remember that the director is
20 inches or 12U high.
Installing the Shelf Brackets in the Rack
The procedure for installing shelf brackets varies depending on the type of rack.
Select the appropriate procedure for your rack type:
■
“
Installing the Shelf Brackets in HP 9000, HP 10000, and HP 11000 Series
■
“
Installing Shelf Brackets in an HP Rack System/e or 19-inch EIA Rack
Installing the Shelf Brackets in HP 9000, HP 10000, and HP 11000 Series Racks
Use these steps to install the two shelf brackets in an HP 9000, HP 10000, or
HP 11000 series rack.
1. Determine the appropriate placement for the director inside the rack.
Note:
HP strongly recommends installing the Director 2/140 in the lowest position in
the rack.
2. Along an exterior vertical rail of the rack cabinet, determine the position of
the bottom of the shelf bracket and count 1U up from this location.
3. Use a straight edge to locate the corresponding rack hole along the interior
vertical rails of the rack cabinet. Mark this location on each interior vertical
rail.