Hardware options installation 52
10.
Route the optical drive cable along the side of the system board, and then connect the cable to the
system board.
11.
Install the primary PCI riser cage ("
Install the PCI riser cages
" on page
24
).
12.
Install the air baffle (on page
22
).
13.
Install the access panel (on page
21
).
14.
Install the server into the rack ("
Installing the server into the rack
" on page
31
).
15.
Power up the server (on page
18
).
Hot-plug fan module option
To provide sufficient airflow to the system if a primary fan fails, the server supports redundant fans.
•
If one fan fails, the system continues to operate without redundancy. This condition is indicated by a
flashing amber Health LED.
•
If two fans fail, the system shuts down.
Summary of Contents for ProLiant DL388e
Page 82: ...Cabling 82 Cabling Storage cabling 4 drive LFF SATA cabling Mini SAS cable Power cable ...
Page 83: ...Cabling 83 4 drive SFF SATA cabling Mini SAS cable Power cable ...
Page 84: ...Cabling 84 6 drive LFF SATA cabling Mini SAS cable 1 and two port SATA cable 2 Power cable ...
Page 97: ...Cabling 97 o Secondary GPU power cabling ...
Page 131: ...Support and other resources 131 ...
Page 132: ...Support and other resources 132 ...