This section contains procedures for installing and cabling the server as a tower unit or in
an 800mm deep equipment Honeywell cabinet, model number MP-C8LCB1 or 1000mm
deep equipment Honeywell cabinet, model number MP-C1MCB1.
Tasks for installing the server
The following table lists the major platform installation tasks.
Table 2-1 Server Installation Tasks
Task
For more information see . . .
Be aware of all power and
grounding requirements for your
furniture.
Specific site requirements
Section 2.2, Power and Grounding Requirements
TPN System Installation (SW20-600), Section 4,
System Grounding
Install tower unit
or
Install the server in the cabinet.
Figure 2-1 for cable connections
Section 2.4, Installing the Server in a Cabinet
Start up the Server
Section 2.7, Start up the Server
If you are remotely connecting
the computer, connect the
remote components.
Remote Peripheral Systems Installation and
Upgrade (RE01)
Before you begin
Before performing the procedures in this section, verify the following tasks have been
performed.
Description
Verify the cabinet has been properly grounded.
Unpack the platform from the box and verify all parts are accounted for.
Use a #2 Philips head screwdriver.
Position the server on a secure surface near the cabinet it will be mounted in.
Identify and verify all necessary cables for your particular configuration are
available.