TRANSPORTING
6-5
LIFTING MACHINE WITH CRANE
WARNING:
•
Do not lift the machine with anyone riding on
the machine.
•
Use wire ropes and shackles strong enough to
support the weight of the machine.
•
Be sure to set the blade position with the
engine running. Failure to do so may cause the
blade to be moved from the set-position when
lifted with a crane.
1. Swing the upperstructure so the blade is positioned at
the rear of the counterweight.
2. Fully retract the blade cylinder.
3. Fully extend the boom, arm and bucket cylinders, as
illustrated to the right. Pull the pilot control shut-off
lever to LOCK position.
4. Position the boom straight ahead of the
upperstructure. Apply the boom swing pedal lock.
5. Attach shackles to the boom and blade hooks.
Securely thread wire ropes through the shackles.
6. Slowly lift the machine so that shock loads will not be
applied to the machine. Take sufficient care not to
loose the balance of the machine.
M1MS-06-002
4680
mm
3000
mm
1130
mm
Summary of Contents for ZAXIS 17U-2
Page 1: ......
Page 7: ...CONTENTS MEMO ...
Page 9: ...MACHINE NUMBERS MEMO ...
Page 39: ...SAFETY S 30 MEMO ...
Page 41: ...SAFETY SIGNS S 32 SS4387344 SS 2901 SS3090482 SS 2869 SS3088058 SS 2870 ...
Page 42: ...SAFETY SIGNS S 33 SS4433590 SS 2871 SS4604981 SS 2872 SS4642517 SS 2873 ...
Page 45: ...SAFETY SIGNS S 36 MEMO ...
Page 53: ...OPERATOR S STATION 1 8 MEMO ...
Page 55: ...BREAK IN 2 2 MEMO ...
Page 71: ...DRIVING THE MACHINE 4 10 MEMO ...
Page 97: ...OPERATION 5 26 MEMO ...
Page 103: ...TRANSPORTING 6 6 MEMO ...
Page 116: ...MAINTENANCE 7 13 7 Swing post M1MS 07 008 ...
Page 165: ...MAINTENANCE 7 62 MEMO ...
Page 167: ...CONSUMABLE PARTS LIST 8 2 MEMO ...
Page 169: ...MAINTENANCE UNDER SPECIAL ENVIRONMENTAL CONDITIONS 9 2 MEMO ...
Page 179: ...REFERENCE 13 2 MEMO ...
Page 183: ...INDEX 14 4 MEMO ...