Shutting down the server you are replacing
On the server that you are replacing:
Procedure
1.
From the server console, issue the command:
shutdown --ship --
powerdown
Wait until the console displays
Information: Server has shut down
,
and the rear panel LEDs turn off. The PSU and server fans continue to
run until you remove the power cables from the PSU module. See the
appropriate system component section for more information.
Note:
This specific
powerdown
command prepares the system for
both shipping, and potential long-term, post-replacement storage.
2.
Unplug the power cords from the power supplies.
3.
Wait approximately 15 seconds, and then confirm the NVRAM status LED
is off.
If the LED is flashing or fixed, press and hold the
reset
button for five
seconds until the LED starts flashing. The battery disables when you
release the
reset
button.
4.
Use the following rear panel figure and table to identify and label the
cabling placement on the existing server.
5.
If cables are not labeled, label them before removing them from the
server.
6.
Remove all cables from the server, and remove the server from the rack.
7.
Remove the rail mounts from the old server, and install them on the new
server.
8.
Remove the battery from the old server, and install it in the new server.
9.
Remove the bezel from the old server, and install it on the new server.
10.
Insert the new server into the rack, and connect the power cords to the
power supplies.
Note:
Do not make any other cable connections at this time.
Configuring the replacement server
Before you begin
Obtain the necessary IP addresses to be used for the replacement server.
Servers shipped from the factory have not yet had the nas-preconfig script
run on them, so a replacement server will not have any IP addresses pre-
configured for your use. You need IP addresses for the following:
Server replacement procedures
111
Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference
Summary of Contents for 3080 G1
Page 6: ...6 Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 11: ...Thank you Preface 11 Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 12: ...12 Preface Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 18: ...18 About this manual Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 27: ...Mandatory regulations 27 Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 28: ...28 Mandatory regulations Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 104: ...104 Hard disk replacement Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 132: ...132 Server replacement procedures Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 137: ...Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...