Server replacement procedures
The replacement of the server as part of a field service process can take
several forms depending on how the system was originally deployed. The
typical field deployment scenarios documented for service replacement
include:
• Single stand-alone server using an embedded SMU for management
• Single stand-alone server using an external SMU for management
• Two-node cluster using an external SMU for management-replacing only
one node
• Two-node cluster using an external SMU for management-replacing both
nodes
Important:
This document does not treat migration scenarios between
different configurations at the time of replacement.
□
Replacement procedure overview
□
Manually installing an internal SMU (if necessary)
□
Replacing a single server with an embedded SMU
□
Replacing a single server with an external SMU
□
Replacing a node within a cluster
□
Replacing all servers within a cluster
Server replacement procedures
105
Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference
Summary of Contents for 3080 G1
Page 6: ...6 Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 11: ...Thank you Preface 11 Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 12: ...12 Preface Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 18: ...18 About this manual Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 27: ...Mandatory regulations 27 Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 28: ...28 Mandatory regulations Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 104: ...104 Hard disk replacement Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 132: ...132 Server replacement procedures Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...
Page 137: ...Hitachi NAS Platform 3080 and 3090 G1 Hardware Reference ...