SAFETY REGULATIONS |
PAG. 5
Once the pole is totally opened, verify the following points:
•
The mast must be totally perpendicular to the ground.
•
The feet must be in touch with the ground.
•
All fixings must be locked.
•
Do not move the tower when the flood lights are on. The high
temperatures that the filaments of the lights reach, make them very
vulnerable to small vibrations, therefore we recommend switching off
the floodlights 1O minutes before moving the equipment.
•
Do not fold the mast of the unit without having lowered it.
•
Do not open the pressure control valve at the bottom of the mast
when it is opened.
2.3 SAFETY DURING INSTALLATION AND FIRST START UP
•
For provisional installations, it will just be enough to place the unit on
a well levelled surface, for installations for a longer period of time, its
advisable to build foundations. The installation of the Generating set
and all its accessories must be carried out by specialized personnel.
lf any difficulty, consult the Himoinsa Technical Department.
•
You must know all the emergency procedures related to the
installation to be done.
•
Always use a protective hard hat, safety boots and gloves, safety
goggles and tight clothes.
•
Do not change the original protections, located on the rotary exposed
parts, over the hot surfaces, air intakes, belts and parts in tension.
•
Do not leave dismounted parts, tools or any other accessory on top
of the engine or nearby or at the premises of the genset.
•
Never leave flammable liquids or cloths soaked with flammable
liquids near the generating set, near electrical devices or parts of the
electrical installation (including lamps).
•
Take all precautions possible in order to avoid flare risks; check that
there is a grounds installation and that has been made according to
Regulations.
•
Place a sign “NO MANOEUVRING” in all the sectioning organs that
insulate the parts of the installation on which you must work.
•
lnsulate all disconnected links and wires. Do not leave uncovered the
voltage terminals of the generator.
•
Connect the grounds installation to all the connexion relative points
prepared in the unit and its accessories.
2.2 SAFETY AT DELIVERY, STORAGE AND UNPACKING
•
Once you receive the lighting tower check that the goods received
correspond to those on the delivery note and that all the goods are in
perfect conditions.
•
To lift and transport the Tower, lifting machines the appropriate
capacity must be used. All loose and pivoting parts must be safely
fixed before lifting it.
•
When moving the lighting Tower and specially when lifting it , it is
recommended to use the available points for its safe and easy
movement.
•
lt is totally forbidden to use any other lifting points located over the
engine, alternator or other components.
•
lf the lighting Tower is damaged for any reason during its
transportation, storage, and/or mounting, it mustn’t be started up
before it is verified by our specialized personnel.
•
lf you want to store the Tower until its utilization, it is highly
recommendable to have a warehouse properly protected against any
chemical agent that may damage its components.
•
Unpacking must be carried out carefully, avoid causing any damages
to the goods during such operation, especially when using levers,
saws or any other metallic tools.
WARNING
Do not place the mast in vertical position, before opening the levelling feet or
before stabilizing the mast over a firm and regular surface. The Tower could
overturn causing serious physical and / or material damages.