Appliance Preparation
CAUTION!
Risk of Cuts, Abrasions or Flying Debris.
Wear protective gloves and safety glasses during
installation. Sheet metal edges are sharp.
WARNING! Risk of Fire!
DO NOT attach elbow directly
to the appliance.
•
The MEZZO36-C/MEZZO36ST-C, MEZZO48-C/
MEZZO48ST-C and MEZZO60-C/MEZZO60ST-C
require a minimum of 18
inches of vertical venting before
attaching any elbow to the appliance.
• The MEZZO72-C/MEZZO72ST-C requires a minimum of
30 inches of vertical venting before attaching any elbow
to the appliance.
4. Place the 1/8 inch thick, square fiberglass gasket over
the initial vent section.
5. Place the fiberglass rope ring over the gasket. Ensure
both the gasket and the rope ring are seated on the top
of the appliance. See Figure 6.2 and Figure 6.3.
Figure 6.2 Location of Fiberglass Rope Ring
Figure 6.3 Fiberglass Rope Ring Installed
GASKET
ROPE RING
A. Top Standoff Preparation
Figure 6.1 Standoffs Shown in Vertical Position
(See-Through Appliance Shown)
1. Rotate the four (4) top standoffs up into vertical position.
60 and 72 only:
Push the standoff support tab on each
standoff toward the center of the appliance and fasten
it in place using the supplied screw and pilot hole. See
Figure 6.1.
Standoff Shipping Position
Standoff Installation Position
2. Place a vent section on the starting collar.
LOCATION FOR INSTALLATION OF
FIBERGLASS ROPE RING
TOP STANDOFFS
STANDOFFS
DOWN
STANDOFFS