4.5 Condensate Connections
•
Provision must be made for removal of condensate from the boiler and flue system.
•
Condense is mildly acidic, typically pH3 - pH5.
•
Condense pipework must be non-corrosive and not copper. Hamworthy recommend
plastic waste pipe.
•
Condense may be discharged to a standard drain subject to National or Local
regulations.
•
Location of condense pipework should prevent freezing within tundishes, traps and
pipework.
•
The connection to the boiler condense drain accepts a straight push-fit coupling for
18mm i.d. plastic waste pipe.
•
Maximum condensate production - 5.1l/hr per 37.5kW & 7.2 l/hr per 50 kW module.
Figure 4.5.1 - Boiler Condensate Connection
Figure 4.5.2 - Flue Condensate Connection
Figure 4.5.3 - Boiler Condensate Connection
Min.
distance
Condensate trap
Condensate
Discharge
pipe
Minimum fall
30mm / m
18mm