CONNECT SERIES SERVICE MANUAL
37
ENGLISH
Maintenance
Model
Time(min)
AUH2436ZGDA
35
AUH4860ZGDA
40
NOTICE:
• Make sure the outlet of vacuum pump is away from fire source and is well-ventilated.
• Before evacuating, make sure the unit cut-off valves are closed.
• When evacuating, both the liquid pipe and the gas pipe must be evacuated.
System Diagram
System Evacuation
1. Remove the caps of the liquid valve, gas valve and also the service port.
2. Meanwhile the gas and liquid valves should be kept closed in case of refrigerant leak.
3. Connect the hose used for evacuation to the vacuum pump.
4. Open the switch at the lower pressure side of the manifold valve assembly and start the vacuum pump.
Meanwhile, the switch at the high pressure side of the manifold valve assembly should be kept closed,
otherwise evacuation would fail.
5. The evacuation duration depends on the unit’s capacity, generally:
Verify if the pressure gauge at the low pressure side of the manifold valve assembly reads 350 microns, if
not, it indicates there is leak somewhere. Then, close the valves fully and then stop the vacuum pump.
6. Wait for 10min to see if the system pressure can remain unchanged. If the pressure increase, there may be
leakage.
Summary of Contents for GE APPLIANCES Connect Series
Page 13: ...CONNECT SERIES SERVICE MANUAL 11 ENGLISH Troubleshooting Model AUH4860ZGDA ...
Page 22: ...CONNECT SERIES SERVICE MANUAL 20 ENGLISH Troubleshooting AUH4860ZGDAA ...
Page 84: ...CONNECT SERIES SERVICE MANUAL 82 ENGLISH Maintenance AUH4860ZGDA ...
Page 96: ...CONNECT SERIES SERVICE MANUAL ENGLISH Appendices 94 ...
Page 97: ...CONNECT SERIES SERVICE MANUAL 95 ENGLISH Appendices ...
Page 98: ...CONNECT SERIES SERVICE MANUAL 96 ENGLISH Appendices ...
Page 99: ...CONNECT SERIES SERVICE MANUAL 97 ENGLISH Appendices ...
Page 101: ......