Inspection 

 

 

13.1 

Periodic checks 

Independently from the regulations of the individual countries, lifting devices must be checked at least yearly 
by a qualified person or licensed qualified person regarding its functional safety.  

 

 

at 

commissioning 

daily 

checks 

1st maintenance 

after 

3 months 

Inspection 

Maintenance 

every 

3 months 

Inspection 

Maintenance 

every 

12 months 

 

check screw connections 

 

 

 

 

check the bearings 

 

 

 

 

 

check the trolley wheels 

 

 

 

 

 

check lubrication of the driving pinion 

 

 

 

 

buffers - check correct position and wear 

 

 

 

 

electric motor* - check the brake lining 

 

 

 

 

 

electric motor* - check the brake 

 

 

 

 

pneumatic motor* 

 

 

 

Have the equipment checked by an expert 

(periodic inspection) 

 

 

 

 

 

*as far as applicable 

 

14 

Service 

 

 

14.1 

Electric motor 

  For  the  motor  it  is  sufficient  to  keep  the  cooling  airways  clean  and  monitor  the  roller  bearing  and  its 
lubrication status. 

A high temperature fat must be used if the roller bearing is replaced. 

 

 

 

   

CAUTION!

 

Brake linings and surfaces must always be clean and fat-free. Even very small amounts of dirt can reduce 
the braking moment considerably. 

 

15 

Trouble 

 

 

Please pay attention to the following in case of problems: 

  Troubles with the equipment must only be repaired by qualified personnel. 

  Secure the unit against unintended operation start. 

  Put up a warning note indicating that the unit is not to be used. 

  Secure the working area of moving parts of the unit. 

  Please read the chapter "Safety instructions". 

Notes on the repair of faults are found in the following table. 

For the repair of failures please contact our service department. 

 

 

 

   

CAUTION!

 

Trouble  caused  by  wear  or  damage  to  parts  such  as  wire  ropes,  chains,  chain  wheels,  axes,  bearings, 
brake parts, etc., must be remedied by replacing the parts with original spare parts. 

 

 

 

 

Summary of Contents for 22/90

Page 1: ...Rev 06 5 52 653 00 01 06 Monorail Trolley 19 90 22 90 push travel trolley 19 90 hand geared trolley 22 90 electric trolley 22 90 E Installation Operating and Maintenance Instructions...

Page 2: ...mation 3 2 Safety 3 2 1 Warning notice and symbols 3 2 2 Duty of care of the owner 4 2 3 Requirements for the operating personnel 4 2 4 Appropriate use 4 2 5 Basic safety measures 5 3 Transport and St...

Page 3: ...efore delivery all products are packed properly Check the goods after receipt for any damage caused during transport Report any damage immediately to the forwarding agent This manual allows a safe and...

Page 4: ...ctional condition and the safety components in particular are checked regularly to ensure that it is functioning properly The required personal protective equipment for the operators service and repai...

Page 5: ...the load Only use the hoists appropriately The equipment is to be used exclusively for movement of goods Under no circumstances my persons be moved Never load the devices beyond their working load lim...

Page 6: ...sible installed in a covered room If they are used in the open protect the units against the effects of weather such as rain hail snow direct sunshine dust etc we recommend to use a cover in parking p...

Page 7: ...ectric trolley 16 4 m min Weights Type bolt Size 500 kg 1 t 1 5 t 2 t 2 5 t 3 2 t 5 t 6 3 t 19 90 N1 4 1 6 8 7 8 7 8 16 6 16 6 31 5 31 5 N2 4 5 8 5 9 9 9 9 19 9 19 9 39 4 39 22 90 N1 5 4 8 1 9 2 10 9...

Page 8: ...uated on the load bars 2 of the trolley Dimension X is set by placing washers 6 from the outer to the inner side X increases or from the inner to the outer side X decreases Washers 6 and rubber discs...

Page 9: ...2 3 mm 1 1 5 mm each side bigger and for trolleys from 4 t up 3 5 mm 1 5 2 5 mm each side bigger than the flange width B of the beam 6 4 Tools 7 Control Only people that are familiar with the operatio...

Page 10: ...bserve the duty cycle i e intermittent operation S3 40 ED as per VDE 0530 means that in a period of 10 minutes the motor can operate no matter the height of the load for 4 minutes It is therefore irre...

Page 11: ...nnection The technical dates of the motors are to be taken from the type plates The wiring diagram is situated in the terminal box Select connection cross sections as per VDE 0100 Put sleeves on the e...

Page 12: ...ing 1 into the shaft slot 2 Insert the feather key 2 into the motor shaft 3 Fix hub 3 with retaining ring 1 4 Assemble the friction plate 4 if existent 5 Push the rotor 5 onto the hub 3 6 Lock the mag...

Page 13: ...sufficient to keep the cooling airways clean and monitor the roller bearing and its lubrication status A high temperature fat must be used if the roller bearing is replaced CAUTION Brake linings and s...

Page 14: ...be changed completely If the unit is suitable for explosive atmospheres the motor must be returned to the manufacturer for repair Air gap is too large Re adjust the air gap If the unit is suitable fo...

Page 15: ...the equipment and any materials it contains is carried out in accordance with environmental regulations 18 Additional documents 18 1 Electric wiring diagrams Electric wiring diagrams are attached to...

Reviews: