14. Table of commissioning checks and operations
* The installation responsible has to verify that safety circuits using control switches and thermostats are on, run properly and switch on at once.
Repeat check procedures:
– at any oil change
– at any exceptional maintenance
– after a continuous stop of 2 or more weeks.
Object
Check
On starting (Categories 2 and 3)
After 24 h and
after one week
(Category 2)
A Oil leaks
(oils seals, joining Visual check
surfaces, plugs, etc)
B External surface
Check by thermometer
temperature
C Noise levels
Sensory check or
preferably by noise-
meter
D Vibrations
Sensory check or
preferably by
accelerometer
E Gear reducer bearings
Check with proper
(unit pre-assembled with
instruments
vibration monitoring device*)
F Cooling coil
Check by thermometer,
chronometer, volume measurer
(or other instruments)
G Oil/air cooling unit
Check air temperature
by thermometer
Visual check:
– direction of rotation of fan
– oil circulation
H Oil/water cooling unit
Check circulation of
water and oil
I Resistance
Check:
thermometers*
– connections to control
(oil, bearings)
–
devices
– setting of devices
– general
functionality
J Oil level control switch*
Check:
– connections
to control
–
devices
– setting of devices
– general
functionality
K Thermostat* (oil)
Check:
– calibration
– electric connections to
–
the safety switch
–
(auxiliary circuits, etc.)
L Cleanliness of external
Visual check
surfaces
M Cooling air passage
Visual check
N Fitting bolts tightening
Check by torque-meter
O Motor absorption
Check by Watt-meter or
amp-meter
Keep under control for the first 4 h
Temporary check
Keep under control the surface temperature until it reaches a
steady condition and verify that
Δ
T
45 K, keep the measu-
red values to compare them in following measurements
Keep under control for the first 4 h. When checking
by an instrument keep the measured values to com-
pare them in following measurements
Keep under control for the first 4 h. When checking
by an instrument keep the measured values to com-
pare them in following measurements
Check on starting and after 4 h. Keep the
measured values to compare them in following
measurements
Keep under control: water temperature
20°C,
water flow rate 10 ÷ 20 dm
3
/min; absence of water
drip
Keep under control for the first 4 h:
air temperature
40 °C;
gauge pressure
0;
absence of oil leaks
Keep under control for the first 4 h: water
temperature
20 °C; water flow rate 15 ÷ 20 dm
3
/
min; gauge pressure
0
Read value of temperature on the control device and
verify that it is lower than the established values.
Keep under control for the first 4 h
Keep under control for the first 4 h
Keep under control for the first 4 h
Dust thickness
0,2 mm
On starting and after 4 h
Check when excessive vibration is detected and
after 4 h
Check on starting and after 4 h.
Keep the measured values to compare them in
following measurements
Measure and com-
pare values with those
previously measured
Check and com-pare
values with those pre-
viously measured
Check and com-pare
values with those pre-
viously measured
Measure and com-
pare values with those
previously measured
Measure and com-
pare values with those
previously measured
Measure and com-
pare values with those
previously measured
Measure and com-
pare values with those
previously measured
Measure and com-
pare values with those
previously measured
Temporary check
Temporary control
Temporary check
Temporary check
Measure and com-
pare values with those
previously measured
Measure and compare
values with those pre-
viously measured
7.1
—
—
—
—
—
—
—
—
—
—
—
—
—
—
Code
Ref
.