background image

Maintenance - Customer Service Section 

GENO

®

 UV systems with GENO

®

-Multi BS 

 

 
 

-CONFIDENTIAL- 

Order no. 034 523 950-gb   Edited by: KONS-mhug-mrie G:\BA-523950-GB_KD-H.DOC 

H-6 

1.3  Overview of maintenance work (every 730 days of operating duration or every 18,000 

operating hours) 

 

All service work and in addition: 

 

Replace UV lamp with GENO

®

-UV 60 S, 120 S, 200 S. 

 

Replace the system sensor and sensor shell (every 730 days of 
operating duration or every 18,000 operating hours, at the 
latest after 2 years).  

 

Replace the flow stabilizer (every 730 days of operating 
duration or every 18,000 operating hours) with operating 
systems with water temperatures between 5 – 30°C. 

 

Record all data and work performed, including repair work, in 
the operation log. 

 

Hand over the system and operation log to the operator. 

 

If possible, if dust deposits have collected remove these from 
the left housing fan carefully from inside to outside with 
pressurised air. 

 

Table H-1: Maintenance work 

Type of maintenance work 

What must be done 

 

 

Check the UV system sensor 
and calibration of the UV 
system sensor Chapter H-2. 

Enter the irradiance indicated in the capacity display into the 
operation log. Check the operating time of the sensor. 

 

If the operating time of the sensor is > 730 days of operating 

duration or 18,000 operating hours, or the last sensor replacement 
took place longer than 2 years ago, the sensor must be replaced. 

Check the functioning of a 
safety device that might be 
installed. 

If the system is switched off, the safety device must close; check 
the water flow. 

Check the functioning of a 
temperature flushing system 
that might be installed. 

Dip the temperature sensor into a beaker with warm water with a 
temperature > the set limit value 

the valve must open. 

UV 200: Check the housing 
fan. 

If filter elements have been added and cannot be cleaned with 
pressurised air, then replace the housing fan (not the ventilator!). 

Replace the UV lamp. 

Replace the UV lamp after 730 days of operating duration or 
18,000 operating hours (see G-1). 

Check the lamp plug. 

Check the lamp plug for fractures and fissures and replace if 
necessary. 

Rinse the UV disinfection 
system. 

Clean the UV system according to the operation manual of the 
flushing set and check the efficiency of cleaning by removing the 
protective quartz tubes and the sensor shell when the system is 
empty. 

Check the seals. 

Check the Viton seal at the protective quartz tube and the O-ring at 
the sensor shell for fractures and fissures and replace if necessary. 

Check the limit value of the 
irradiance. 

Check the limit value of the irradiance according to table E-1 and set 
it as specified in the customer service section, chapter E-6 if necessary. 

Check the pre-alarm of the 
irradiance. 

If the limit value is o. k., slowly pull the sensor out of the sensor 
shell. With 10% above the set limit value the red pre-alarm LED 
must start to light up. Reset if necessary as specified in the 
customer service section, chapter E-6. 

Documentation. 

Record all data and work performed, including repair work, in the 
operation log. 

 

Summary of Contents for GENO-UV 120 S

Page 1: ...section consists of a lose collection of sheets that should according to the respective chapter and page number refer to header and footer be attached to the corresponding chapters of the standard ope...

Page 2: ......

Page 3: ...device For determination of the SAK254 please send a water sample of at least one liter to our internal lab The testing of the UV systems for the disinfection of drinking water is carried out at a des...

Page 4: ...tested by the DVGW is maintained Table E 1 Indicator points certified by the DVGW System SAK254 10 50 100 max flow min irradiance m 1 m h W m GENO UV 60 S 2 7 94 0 74 1 55 0 3 3 11 5 GENO UV 120 S 8 0...

Page 5: ...rating panels and display 2 2 Operation programming level 2 3 Installer level code 290 2 4 Error memory code 245 2 5 Displaying the software version code 999 2 6 Customer service level code 302 2 7 Re...

Page 6: ...level Key Display Unit LED Basic display of irradiance XX XX W m X Operating duration XXXX Days X Switch on processes XXXX X Time until service is due XXXd Days Back to basic display of irradiance or...

Page 7: ...d parameter while value flashes Return to the next parameter Close the opened parameter without saving the old set value is main tained Jump back to the basic display of irradiance Open the display of...

Page 8: ...or the menu to be edited The code for the level required here is 290 2 Press key to count upwards until C 290 appears in the display OR Press key to count downwards until C 290 appears in the display...

Page 9: ...hould be reset so that they display the code for the menu to be edited The code for the level required here is 245 2 Press key to count upwards until C 245 appears in the display OR Press key to count...

Page 10: ...l code 302 Index Parameter Unit Factory setting Setting range Note 0 Calibration of UV sensor W m Current irradiance 0 45 0 see chapter H 2 1 1 Irradiance limit value W m According to currently set da...

Page 11: ...ooting This is what you observe This is the cause This is what to do Er 1 and UV lamp light up Irradiance limit value System is dirty inside Service life 730 days or 18 000 h of UV lamp has been excee...

Page 12: ...20 mA interrupted UV sensor connection plug in serted correctly Optional USB data recording device wired incorrectly Er 6 or Er 7 Wire fracture or short circuit of the temperature sensor only when the...

Page 13: ...Check seals and replace if necessary Check functioning of the safety device Check functioning of a possibly existing rinsing valve Rinse UV disinfection system if required Clean protective pipes if ne...

Page 14: ...afety device that might be installed If the system is switched off the safety device must close check the water flow Check the functioning of a temperature flushing system that might be installed Dip...

Page 15: ...ation log On the GENO Multi BS control unit change to calibration level code 302 and open the parameter 0 XX X with the key P for editing 0 XX X flashes Remove the system sensor insert the reference s...

Page 16: ...Edited by KONS mhug mrie G BA 523950 GB_KD H DOC H 8 3 Resetting the operating hours and the switch on counter After replacing the lamp the operating duration and switch on counter should be reset Rep...

Reviews: