Removal operation for 4-way valve
Remark: Before removing the 4-
way valve, please make sure that there’s no refrigerant inside the pipeline of system and
then power is disconnected.
Process
Photo
Operation Instruction
1)Disconnect
the coil of 4-way
valve from the
4-way valve
●Remove the coil of
4-way valve at first
2)Disconnect
the 4-way valve
and connection
pipeline
● Weld those 4
connection spots on
4-way valve, and then
pull out the
connection pipe
Note: During welding
process, do not let the
flae burn out other
parts
3) Replace
4-way valve
● Replace 4
-way
valve
Note: During welding
process, do not let the
flame burn out other
parts
Summary of Contents for GMV-100WL/A-T
Page 1: ...DC INVERTER VRF SYSTEM SERVICE MANUAL R410A...
Page 4: ...DC INVERTER VRF SYSTEM II SERVICE MANUAL R410A PRODUCT...
Page 16: ...GREE DC Inverter Multi VRF System II Service Manual 12 GMV 141WL C T...
Page 18: ...GREE DC Inverter Multi VRF System II Service Manual 14 CONTROL...
Page 64: ...GREE DC Inverter Multi VRF System II Service Manual 60 INSTALLATION...
Page 72: ...GREE DC Inverter Multi VRF System II Service Manual 68 DEBUGGING MAINTENANCE...
Page 173: ...JF00302323...