INSTALL THE INNER DOOR:

STEP 10

. Create two cushioning blocks for the inner

door installation. Use the cardboard from the box and

cut, tape and assemble two 3/8” to 1/2” thick 6” x 6” 

blocks.

STEP 11.

The inner door is installed from the 

inside with the twin rollers facing out. Lift the door

over the curb and angle it to the inside. Working

from each side of the door lift and tip it (about 15 to

25 degree angle is necessary) so that the rollers on

both sides of the door move up and into the desig-

nated channel. As you lower the door into the track

move the position to vertical and rest on the 

cushioning blocks on the curb. Tighten the back

screws of the rollers with the wrench supplied. 

Remove the cushion blocks.

From the inside-- Lift the inner door with

rollers assembled and set the rollers inside the

groove on the inner side of the header in the

manner shown.
The glass door must be angled - 15-25 degrees.

The rollers must go in and up into the upper

cavity of header. Swing the bottom of glass 

forward to parallel it with header until both

rollers are inside the groove bring the glass

and rest it on the cushion blocks on the curb.

When the glass door is

resting on the blocking

and rollers are inside the

header use the Roller

Wrench to tighten the

screws on the back of the

rollers.

After tightening the screws

with the  Roller Wrench

remove the blocks under

the doors.

Cut 4 strips of cardboard 6"x 6”

and tape 2 of them together

making 3/8”-1/2” thick 6” x 6”

blocks. Make 2 blocks out of 4

strips.

Set two 3/8”-1/2”

blocks (not provided)

on curb top (as

shown).  Use the

cardboard from the

boxes that glass was

shipped in for the

blocking. 

Detail 10A

Detail 11A

Detail 11C

Detail 11B

Move the inside stops to the ends of the header and

temporarily snug them in place to prevent the Glass

from hitting the wall during installation.  

Final stop adjustment is done in step 18.

(NOT SHOW HERE) 

Inner and Outer Door Roller

Stops must be in the end of

the header and tightened

just enough to hold in place.

Summary of Contents for Equalis series

Page 1: ...sinc com or 888 683 1362 Monday thru Friday from 8 00 am to 5 00 pm EST Installation shall be made according to manufacturers instructions and drawings GlassCrafters recommends the installation be performed by a trained installer Revised110 2018 WARNING TO INSTALL ON CAST IRON FIBERGLASS ACRYLIC OR RESIN TUB OR SHOWER BASE Check with the tub or shower base manufacturer to determine the tooling req...

Page 2: ...ns for safe installation Always wear safety glasses during this installation The proper dimensions for this installation were submitted at the time of order The two doors may overlap to accommodate minor smaller opening One end of the Header many be cut with a Hacksaw for stainless steel but it must fit completely in the Header Wall Brackets for a safe installation When installing any mechanical pa...

Page 3: ...be use to open any box Please remove all staples from the box prior to unpacking metal and glass Stand Panels upright on a cushioned base such as a piece of carpet or towel Never place glass directly on hard surfaces Any assembly that requires the panel to lay flat must be on a cushion surface IMPORTANT Read all instructions carefully and become familiar with all parts before installation 1 Header ...

Page 4: ...Use a level to determined that the enclosure is plumb on both sides If any side is out of plumb more that 3 8 it will make the adjustment of the Glass Doors complicated Detail 1A Detail 1B Detail 1C Extend the centerline from the high side of the curb on the wall Determine the high side Find the Midpoint of the Curb and mark a pencil line from front to back Find the Centerline of the curb and mark...

Page 5: ... unit Place the bracket in position on the centerline and mark holes for the wall bracket 76 high unit 66 high unit NOTE Loosen the set screws and the bracket top slides out for installation After drilling the holes for the Header Bracket add silicone to each hole and put the anchors in place FOR MODELS USING A RETURN PANEL Stop here and read the installation manual for the RETURN PANEL The Return...

Page 6: ...s level The difference will be the out of square measure at the curb Use a level to determine the exact position as follows Place the second side wall Header Bracket on the Header loosen the set screws to slide onto the Header and place the other end of Header in the installed Wall Bracket NOTE When placing the header into the bracket squeeze each end to be sure that the stainless steel cladding is...

Page 7: ...mine that it is exactly parallel to the center line for the Center Guide The offset from the centerline should be 1 15 32 1 4686 The Center Guide and the Curb Dam must be installed at the same time See Step 12 Detail 6A NOTE Do not install the Center Guide at this time See Step 12 Detail 6B Center Guide and Curb Dam Assembly Shown from outside view Detail 6C Curb Dam Shown end view Double Faced Tap...

Page 8: ...nstall the header in the wall brackets insert the brack covers and tighten the set screws Be sure the header rest firmly on the bottom of the bracket and that it is exactly level Detail 7A Shows inside of the Header Detail 8A Detail 8B Detail 8C Outer Door Roller Stops Inner Door Roller Stops Inner Door Roller Stops to each end of the header and tighten just enough to hold in place Outer Door Rolle...

Page 9: ...ust only be hand tight Detail 9D Detail 9C Top View Detail 9D Section View Detail 9A Install the inner rollers on the inner glass door Do not tighten the back screws of inner roller assembly The roller assembly must be loosely fixed on glass at this time Detail 9B Inner Roller Assembly Exploded View Detail 9C Inner Roller Assembly as supplied assembed Do not tighten the back screws of inner roller ...

Page 10: ...15 25 degrees The rollers must go in and up into the upper cavity of header Swing the bottom of glass forward to parallel it with header until both rollers are inside the groove bring the glass and rest it on the cushion blocks on the curb When the glass door is resting on the blocking and rollers are inside the header use the Roller Wrench to tighten the screws on the back of the rollers After ti...

Page 11: ...ment holding the Center Guide in position STEP 13 Lift out the parts and drill the hole for the Cen ter Guide Insert a small amount of silicone and the An chor Wipe the base clean of all debris Clean surface with denatured alcohol Do Not remove the pencil marks for the outside of the Curb Dam Centerline Pencil line for Curb Dam position Position the Curb Dam pencil mark for outside edge 1 15 32 fr...

Page 12: ... Turn the Curb Dam over Remove the film covering the double faced tape Carefully align and place on the curb to the pencil marks Fit the Center Guide into place sliding it over the Curb Dam and under the Inside Door Retest the movement of the Door side to side through the Center Guide Screw the Center Guide into place and press the Curb Dam firmly into place Double Faced Tape Replace the plastic cov...

Page 13: ...IN THE CENTER OF THE ROLLER AS VIEWED FROM THE INSIDE ARE PERPENDICULAR TO THE EDGE OF THE GLASS See Detail 15C Do not install the Outer Roller Cap or the Outer Roller Back Plate and screw until after the doors are finally adjusted 90 00 Detail 15B Detail 15C As viewed from the inside of the door BE SURE THAT THE ANTI LIFT SCREW GROOVES IN THE CENTER OF THE ROLLER AS VIEWED FROM THE INSIDE ARE PERP...

Page 14: ... smooth operation tighten the inner door roller screws and place the Inner Roller Cap Detail 16E over each Inner Roller Fix the Inner Roller Cap in place with the set screw Install the Outer Roller Cap Detail 16F and the Outer Roller Back Plate as shown in the Illustrations Fix the Outer Roller Caps and Back Plates in place with the set screws 14 Detail 16B Side View Detail 16E Install the Inner R...

Page 15: ...n the screws for the door stops for this closed position Carefully move the doors to the opposite ends of the header leave 1 2 to 1 gap between this position and the wall and tighten the second set of stops at this end of the header for both doors 15 Detail 17A A Vinyl Detail 17C Shows A Vinyl in place Detail 18A Shows Doors in closed Position Detail 18B Shows Doors fully open with 1 2 gap to the ...

Page 16: ... is need to keep your shower tub enclosure looking brand new EQUALIS Series Models Catalog Number PSS Polished Stainless Steel BSS Brushed Stainless Steel CHA Polished Chrome Anodized IBK Black Iron Shower Enclosures Metal Finish DS 48T 38 PSS DS 48T 38 BSS DS 48T 38 CHA DS 48T 38 IBK DS 54T 38 BSS DS 54T 38 PSS DS 54T 38 CHA DS 54T 38 IBK DS 60T 38 PSS DS 60T 38 BSS DS 60T 38 CHA DS 60T 38 IBK DS...

Reviews: