CHAPTER 1: AC POWER MEASUREMENT
GE Multilin
EPM 5000 series Advanced Power Meters
3
Voltages between the phases vary depending on loading factors and the quality of distribution
transformers. The three-phase system is distributed in different voltage levels: 208V AC, 480V AC, 2400V
AC, 4160V AC, 6900V AC, 13800V AC, and so on.
Power measurement in a poly phase system is governed by
Blondel's Theorem
. Blondel’s Theorem
states that in a power distribution network which has N conductors, the number of measurement elements
required to determine power is N-1. A typical configuration of poly phase system has either a Delta
connection or a Wye connection (see
Figure 1.4
, below).
N
A
B
C
2) Wye
X
E I
CN C
X
X
P = E I + E I + E I
AN
BN
CN
E I
BN B
E I
AN A
B
A
C
1) Delta
X
X
E I
CB C
E I
AB A
P = E I
AB A
+ E I
CB C
A
B
C
Figure 1.4
: Poly Phase System: (1) Delta, (2) Wye
1.3: Consumption, Demand and Poor Power Factor
CONSUMPTION
:
T
W
=
WH
×
W
= instantaneous power
T
= time in hours
The total electric energy usage over a time period is the consumption of WH.
Typically, the unit in which consumption is specified is the kilowatt-hour (KWH): one thousand watts
consumed over one hour. Utilities use the
WH
equation to determine the overall consumption in a billing
period.
DEMAND
: Average energy consumed over a specified time interval. The utility determines the interval,
typically 15 or 30 minutes. The utility measures the maximum demand over a billing period. This
measurement exhibits a deviation from average consumption, causing the utility to provide generating
capacity to satisfy a high maximum consumption demand. The highest average demand is retained in the
metering system until the demand level is reset.
POOR POWER FACTOR
: Results in reactive power consumption. Transferring reactive power over a
distribution network causes energy loss. To force consumers to correct their Power Factor, utilities
monitor reactive power consumption and penalize the user for Poor Power Factor.
Summary of Contents for EPM 5200
Page 2: ......
Page 30: ...CHAPTER 4 COMMUNICATION INSTALLATION 26 EPM 5000 series Advanced Power Meters GE Multilin ...
Page 70: ...CHAPTER 10 PROGRAMMING GROUP 1 66 EPM 5000 series Advanced Power Meters GE Multilin ...
Page 88: ...CHAPTER 14 EXITING PROGRAMMING MODE 84 EPM 5000 series Advanced Power Meters GE Multilin ...
Page 94: ...CHAPTER 15 PROGRAMMING QUICK REFERENCE 90 EPM 5000 series Advanced Power Meters GE Multilin ...