Modifications reserved
Pagina 85/90
OPM_SPE_XXX_60K_60K_7GB_V010.doc
Operatine Manual
SitePro 60 kVA
10.5.2 Top cable entry box
Fig. 10.5.2-1 Top cable entry box assembly
In case the power cables enter the UPS cabinet by the top, an optional
“
Top Cable Entry Box”
must be
provided:
•
Remove the bottom grid
“
A
”
from the left side of the UPS cabinet.
•
Locate the piece
“
B
”
against the left side of the UPS cabinet and hook it up to the slits at the top of
the UPS cabinet.
•
Drill the removable cover
“
D
”
with appropriate hole and install the cable glands (not provided with
the equipment).
•
Run the power cables through the cable glands, feed them through the aperture at the bottom of
the UPS cabinet and connect them to the input/output terminals.
•
Fix the side cover
“
C
”
and the top cover
“
D
”
using the screws fitted on both sides.
If the UPS is equipped with
optional
“
5
th
Harmonic Input Filter or 5
th
+ 11
th
Harmonic Input Filter”
cabinet, the
“
Top Cable Entry Box
”
must be installed against the left side of the filter cabinet.
If the UPS is equipped with additional cabinets, the optional “
Top Cable Entry Box
”
must be installed
against the left side of the first cabinet on the left.