BP Special Version Dispenser
Supply & Installation Procedure
Updated 24/06/98 / 21/07/98 / 30/04/99 05/05/99
File @ GME c:/pec/apollo/instal1.doc
PEC will supply required Components to site.
Components include;
Sump Box with Delivery Ducts & Internal Delivery Pipe Assys
fitted
Sump Box Lid
Bulkhead Seals
Sump Box Lid with Handles
Sump Cover & Sub-frame with divider skirt fitted
Main Wiring Looms & Junction Box (fitted into Sump Box)
Cable Feed Flexible Conducts (40 & 50 mm Dia) with Fittings
Stage 1 - Installation Procedure
•
Install Sump Box into position below ground level as shown
•
Centralise Sump, with Box end Face to Column Face at a distance of 300mm
•
Secure Cable feed Flexible Conduit to Sump Box (if not already fitted) (Later version
one piece fixed Cable Duct)
•
Install Internal Delivery Pipe Assys into ducting (if not already fitted)
•
Plug or cover Delivery Ducts to stop foreign matter entering
Sump Box
Forecourt
Surface
785 mm
+/- 10mm
300 mm
+/- 15 mm
Column
Delivery Ducting
89945
20 mm out
from Column
50 mm Above Ground
Cable
Duct
Summary of Contents for Apollo 3000
Page 1: ...Apollo 3000 Set up Installation Parts Manual...
Page 2: ......
Page 4: ......
Page 15: ...11 Float Switch 89778 Float Swt Mtg Angle only 89749 Float Switch Bracket Assembly...
Page 26: ...22 Stage 1 Installation Procedure Sump Column Position Fig 2...
Page 27: ...23 file gme c docum pec apollo2 fig 2 manual doc Stage 1 Installation Service Area Spec Fig 3...
Page 28: ...24 Stage 1 Installation Procedure Mounting Positions Fig 4...
Page 29: ...25 Stage 3 Vent Box Installation Vent Box Position Sealing Spec Fig 5...