MAINTENANCE - 4
4.4.1
ELEMENT REMOvAL
Figure. 14 - Boiler Element Removal
Isolate and completely drain the boiler (see
Section 3.5 - Draining the Boiler)
before removing
the boiler heating elements.
Remove the four element securing nuts from the element mounting flange. Element is now loose
for removal from the boiler.
The elements will need removing to carry out internal inspections of the boiler and to complete
element checks mentioned in
Section 4.4 - Element Care and Protection.
Boiler heating
element
Element power
supply terminals
Element
mounting flange
Element securing
nut