![Froling Turbomatic TMC 100 Installation Instructions Manual Download Page 37](http://html1.mh-extra.com/html/froling/turbomatic-tmc-100/turbomatic-tmc-100_installation-instructions-manual_2338740037.webp)
Initial startup / Decommissioning
Fröling Heizkessel- und Behälterbau Ges.m.b.H, Industriestrasse 12, A-4710 Grieskirchen
Page 37
Tel +43 (0) 7248 606-0 Fax +43 (0) 7248 606-600 [email protected] www.froeling.com
M1020008_en
4
4
Initial startup / Decommissioning
4.1
Configuring the boiler
The boiler must be adjusted to the requirements of the heating system
during commissioning
NOTICE
Optimum performance and efficient operation with low emissions can only
be guaranteed if the system is set up by a qualified technician and the
specified factory settings are observed.
Take the following precautions:
U
We recommend that the system is commissioned by Fröling customer
services or an authorised installer.
Before heating up the boiler for the first time:
U
Adjust the control unit to the system type
The keypad assignment and the steps necessary to modify the control
parameters are detailed in the accompanying operating instructions for
the boiler control unit.
4.2
Mothballing
If the boiler is out of service for several weeks (e.g. during the
summer), we recommend that you perform the following maintenance
tasks:
U
Carefully clean the boiler
U
Completely close all doors and flaps
If the boiler is to remain out of service during the winter:
U
Have the system completely drained by a qualified technician
´
Protect against frost!
4.3
Disassembly
To disassemble the boiler, perform the assembly steps in reverse order.
À
Installation steps see 3.3 Assembly work
4.4
Disposal
U
Dispose of all waste in an environmentally-friendly manner and in
accordance with waste disposal regulations.
U
Separate and clean recyclable materials and send them to a recycling
centre.