5.4.2 Recommended clearances in the boiler room
▪ The system should generally be set up so that it is accessible from all sides
allowing quick and easy maintenance.
▪ Regional regulations regarding necessary maintenance areas for inspecting the
chimney should be observed in addition to the specified distances!
▪ Observe the applicable standards and regulations when setting up the system.
▪ Observe additional standards for noise protection!
(ÖNORM H 5190 - Noise protection measures)
EF 250
EF 500
A
B
C
A
C
B
D
Description
A
Ash container maintenance area
200 mm
B
Left maintenance area
400 mm
C
Geared motor maintenance area
200 mm
D
Right maintenance area
1)
400 mm
1.Only for electrostatic precipitator system EF 500
Assembly
5
Setting up in the boiler room
Installation and Operating Instructions EF 250-500 | M2140120_en