Installation
(for qualified installers only)
1 7
Travis Industries
9 3 5 0 8 1 1 6
0 3 1 0 0 0
Vent Installation
•
In addition to the requirements below, follow the requirements provided with the vent.
Use a firestop whenever
passing through a ceiling
Vertical Termination
Use a roof flashing and storm collar
whenever passing through the roof
Use a support box
on exposed vent
Vertical Vent
Requirements
Use a wall thimble
whenever passing
through a wall
Horizontal Termination
Maintain a minimum 1" clearance (2-1/2"
in some cases - see "Clearances") from
vent to any combustible
Minimum
Framing
Horizontal Vent
Requirements
Minimum framing
for fire stop
Maintain a minimum 1"
clearance from vent to
any combustible
8-5/8"
or
10"
8-5/8"
8-5/8"
or 9"
8-5/8"
•
Slide the vent sections together and turn 1/4 turn until the sections lock in
place.
•
Screws are not required to secure the vent. However, three screws may be
used to secure vent sections together if desired.
•
High temperature sealant is recommended at the appliance starter section
connection (use high-temperature silicone or Mill-Pac®).
•
If disassembly is required, at time of re-assembly check to see if the vent
creates a tight fit. If it does not, apply high temperature sealant to the joints of
the affected sections.
•
Horizontal sections require a 1/4" rise every 12" of travel
•
Horizontal sections require non-combustible support every three feet (e.g.: plumbing tape)