21
GB
KJ 73-A
75036141 - KJ 73-A – rev 01 - ( 02-2021 )
MAINTENANCE
Daily maintenance
- Check that the threaded tie rod is not damaged.
- Check the supply system of the compressed air.
- Check that the stroke of the tool is suitable for the selected insert to clamp (see the pertaining instructions for adjusting
the stroke, indicated at page 15).
- Check that there are neither air nor oil leakages. In this case replace possible damaged connectors or seals.
- Check that the supply pressure of the compressed air does not exceed
101.5 psi.
Weekly maintenance
- Check the oil level by verifying that the riveter stroke meets the minimum requirements of
.393"
without insert inserted
(fig.
f16
). If the check does not meet the minimum requirements, repeat the oil filling procedure (fig.
f15
).
Overhaul of the riveting tool
It is advisable to carry out a complete overhaul of the riveting tool after
600,000 cycles
or
every year.
In this case apply only to centres authorized by
FAR S.r.l.
DISPOSAL OF THE RIVETING TOOL
Follow the prescriptions of the national laws for disposing of the riveting tool.
After disconnecting the tool from the pneumatic system, disassemble and split all the components according to the
material: steel, aluminium, plastic material, etc.
Then proceed to scrap the materials in accordance with current laws.
Procedere quindi alla rottamazione nel rispetto delle leggi vigenti.
f16
.393" (+ 0.008 )
0