background image

6

PIC. 8

PIC. 10

PIC. 9

SB

SB

PIC. 11

®

Once the concrete has set, put the combined unit in the enclosure and screw it down by means of the two long bolts supplied with the
equipment, see picture No. 10.

Attention

: follow the wiring and connecting procedure on page 9 and picture 18. Allow the operators to run full movement 3 times before

hanging the gates. Weld the fixing plate to the gate, either the non-locking type or locking type, which can be released for emergency.
Picture 8 or 9.

WELDING

LOCKING SHOE IN
RELEASED POSITION

OR: NON LOCKING GATE
FIXING PLATE WITH
SHAFT FITTING COLLAR

BOX SPANNER

LONG BOLTS COMBI 740

SB

RELEASE

Once satisfied that everything has been done as described so far,
make sure that the two units are mounted on the correct side of the
gate, view from inside the property: the unit marked “D” on the right-
hand side and “S” on the left-hand side. The COMBIs are designed
as handed operators, the correct position is essential to the
performance of the system. Picture 11.

L

 HAND RELEASE

HYDRAULIC RELEASE
FOR THE FIRST OPERATIONS

“S”

JACK/PUMP
LEFT-HAND SIDE

R

 HAND RELEASE

HYDRAULIC RELEASE
FOR THE FIRST OPERATIONS

“D”

JACK/PUMP
RIGHT-HAND SIDE

GATE STOP

VIEW FROM INSIDE THE PROPERTY

Summary of Contents for COMBI 740

Page 1: ...B Instruction manual COMBI 740 Oil hydraulic operator for swinging gates Below ground Version with two way locking device Version with brake in open close cycles Version with 110 and 175 shaft rotatio...

Page 2: ...RE VALVE CLOSE SAFETY PRESSURE VALVE OPEN VALVE COVER TWO WAY LOCKING VALVE ASSEMBLY MOTOR END PART MOTOR END PART PUMP SHAFT MOTOR BASE FLANGE SUCTION FILTER OIL RESERVOIR ELECTRIC MOTOR HYDRAULIC LO...

Page 3: ...IL RESERVOIR PLUG OIL RESERVOIR END CAP WIRE CONNECTORS HYDRAULIC OIL ARNICA A 15 BY AGIP ELECTRICAL CABLE RIGHT HAND JACK END CAP DAMPENING ADJUSTMENT ELBOW JOINT BEARING TOOTHED MAIN SHAFT CENTRAL B...

Page 4: ...6 LH 747 LH 746 RH 747 RH GATE SPACER HINGES NYLON WIRE It is recommended to keep to these instructions to install the equipment in the correct way to get a perfect working system Electro hydraulic op...

Page 5: ...close to the gate post dimensions as indicated in picture No 5 and lay the enclosure in it perfectly horizontal with the help of a level The upper edge of the enclosure must be levelled with the pavem...

Page 6: ...IN RELEASED POSITION OR NON LOCKING GATE FIXING PLATE WITH SHAFT FITTING COLLAR BOX SPANNER LONG BOLTS COMBI 740 SB RELEASE Once satisfied that everything has been done as described so far make sure...

Page 7: ...prevent misuse See pictures No 12 13 With single gates the electric lock is to be installed horizontally in the most suitable way to meet the application requirements Double gates can be fitted with a...

Page 8: ...AMPENING DAMPENING DEVICE OUT OF SERVICE IN SERVICE OIL FILLER CAP JUNCTION BOX CUT OUT BRICKWORK TO PROVIDE PROTECTION FOR THE CONTROL BOX Should the model with the dampening device be required to in...

Page 9: ...OR RUN OPEN CLOSE TIME CAPACITORS MICROPROCESSOR DIP SWITCH TERMINAL FOR CONNECTIONS TO PUSH BUTTONS PULIN 3 1 AMP FUSE 24 V OUTPUT TERMINALS 12 13 TIMER SWITCHES FUSE 630 mA FUSE 5 AMPS 1 st CHANNEL...

Page 10: ...Hz CONDENSER 12 5 F RED YELLOW GREEN BLUE RED CONNECT THE ENCLOSURE EARTH WIRE 2 1 3 10 PIC 21 PIC 20 SPECIAL VERSIONS FLOW REGULATORS FOR COMBI 740 MANUAL TEST FOR COMBI 740 ADJUSTMENT SCREW FLOW REG...

Page 11: ...HYDRAULIC PUMP Pump flow rate P3 0 85 l min Working pressure 1 MPa 10 bars Max pressure 3 MPa 30 bars Working temperature 20 C 80 C Rotation time 110 23 s Oil type A 15 FADINI by AGIP Shaft rotation a...

Page 12: ...TOTAL QUALITY CONTROL system which ensures constant quality standards updated knowledge of the European Standards and compliance with their requirements in view of an ever increasing process of impro...