6.5 WALL SET-UP
T
he station can be mounted using:
▫ a base built by the installer
▫
an optional plinth
6.5.1. Construction of the base
6.5.1.1
Recommendations for the construction to be followed
≥
10 cm
Ø
e
a
b
f
i
h
g
d
c
l
k
m
Rj
1
Figure 11 - Dimensional recommendations for the APS base
Pos Element
1
T
he area planned for cable routing inside
the station.
Ref.
Mm
Inch
a
708
27" 7/8
b
21
53/64
c
140
5" 33/64
d
551
21" 11/16
e
M12
M 0" 1/2
f
40÷400
1" 37/64÷15" 3/4
g
750
29" 17/32
h
140
5" 33/64
i
200
7" 7/8
j
r50
r 1" 31/32
k
147
5" 25/32
l
550
21" 21/32
m
380
14" 61/64
Leave at least 10 cm between the
station and the wall behind it to allow
proper ventilation ( Position of
devices)
The minimum height (f) of the base
allows you to observe the instructions
provided by ISO and ADA standards
for disabilities.
Do not exceed the maximum height.
I
f the station is installed in a safety evacuation corridor, make sure that when the product's door is open, there is still
enough room to pass (
Position of devices
).
Summary of Contents for PARQUBE APS
Page 2: ......
Page 7: ...7 68 Ver 1 1 January 2017 en US Chapter 1 MANUAL INTRODUCTION ...
Page 10: ...10 68 Ver 1 1 January 2017 en US This page is intentionally left blank ...
Page 11: ...11 68 Ver 1 1 January 2017 en US Manual introduction Chapter 2 GENERAL CONDITIONS ...
Page 17: ...17 68 Ver 1 1 January 2017 en US Chapter 3 STORAGE AND HANDLING ...
Page 24: ...24 68 Ver 1 1 January 2017 en US This page is intentionally left blank ...
Page 25: ...25 68 Ver 1 1 January 2017 en US Chapter 4 PRODUCT DESCRIPTION ...
Page 36: ...36 68 Ver 1 1 January 2017 en US This page is intentionally left blank ...
Page 37: ...37 68 Ver 1 1 January 2017 en US Chapter 5 ACCESS TO THE PERIPHERAL ...
Page 42: ...42 68 Ver 1 1 January 2017 en US This page is intentionally left blank ...
Page 43: ...43 68 Ver 1 1 January 2017 en US Chapter 6 INSTALLATION ...
Page 60: ...60 68 Ver 1 1 January 2017 en US This page is intentionally left blank ...
Page 61: ...61 68 Ver 1 1 January 2017 en US Chapter 7 SETTINGS ...
Page 64: ...64 68 Ver 1 1 January 2017 en US This page is intentionally left blank ...
Page 65: ...65 68 Ver 1 1 January 2017 en US Chapter 8 DECLARATION OF CONFORMITY ...
Page 67: ...67 68 Ver 1 1 January 2017 en US This page is intentionally left blank ...
Page 68: ...HUB Parking Technology a Business Unit of the FAAC Group www hubparking com ...