ENGLISH
T
ranslation of the original instructions
14. Set the F003 DECELERATION TIME and A021 OPERATING SPEED in the inverter (see section 12.2)
15. Do not modify the deceleration points (ROP/RCL) and/or stops (FCO/FCC) before having set the deceleration time and speed of the
inverter (see section 12.2)
16. Tighten the central locking screw of the limit switch unit (Fig. 22 ref.
).
17. Manually place the sliding leaf at half its travel and ensure that the limit switch position corresponds to Fig. 21
18. Refit the limit switch cover.
19. Manually close the sliding leaf.
20. Prepare the operator for NORMAL operation, as described in section 8.
21. Ensure that there is no danger and the safety devices are operating correctly.
22. Give an OPEN pulse and verify correct operation.
The maximum adjustable STOP SPACE is 5 m.
The operator is supplied with factory settings for automating gates with RIGHT-HAND opening. If the gate
requires LEFT-HAND opening, the association of the related opening and closing limit switches is reversed. For
these operations, follow the instructions contained in paragraph 11.4.9 Reversing Gate Opening Connections
from Right to Left.
FCO = opening limit switch (screw
)
FCC = closing limit switch (screw
)
ROP = start of opening deceleration (screw
)
RCL = start of closing deceleration (screw
)
Fig. 20
Fig. 21
Fig. 22