background image

T

HE

 455 D C

ONTROL

 P

ANEL

 

 

G

ENERAL

 D

ESCRIPTION

 

 

The FAAC 455 D control panel is used to operate the 

following models. 

 

 

Swing gate operators

400  

412 

402  

750 

422  

760 

 

 

Barrier gate operators: 

 

 

610/615

 

 

The 455 D programming controls the following: 

 

Operating logic

: A, S, E, EP, B, and C logics 

available. 

 

Reversing device behavior

: Choose whether a 

triggered reversing device during closing 

immediately reverses gate movement or stops the 

gate and reverses gate movement when no longer 

triggered. 

 

Torque or Pressure

: Force adjustment for the 412 

operator. Adjustable from 0 to 50. 

 

Caution

: For all hydraulic operators, the torque  

must

 be programmed to the maximum (50) setting. 

  

Pause time between opening and closing

adjustable from 0 to 240 seconds. 

 

O p e n i n g / C l o s i n g   t i m e

:   a d j u s t a b l e 

 

from 0 to 120 seconds. 

 

Leaf delay on closing

: adjustable from 0 to 4.1 

minutes. 

 

The 455 D control panel should be installed in an 

enclosure that is conveniently located as close as 

possible to the gate operator. All electrical connections 

from the control panel to the operator must be made in 

a weatherproof junction box. 

 

The 455 D control panel requires a single-phase power 

supply voltage (115 VAC [±10%] or 230 VAC [+6 or -

10%], 50–60 Hz). The power supply should be protected 

by a 15 amp dedicated circuit breaker (not provided). 

 

The installer is responsible for grounding the 

operator system, for providing the main power 

breaker switch, and for making sure that the entire 

gate system meets all applicable electrical codes. 

The installer should refer to the installation manual 

for a given operator for more information

 

N

OTE

An installation is U.L. compliant only 

when you install the FAAC operators according 

to the UL325 standards. 

 

I

NSTALLING

 

THE

 455 D C

ONTROL

 

P

ANEL

 

 

Locate the control panel in the most convenient position 

possible, considering the movement of the gate.   

 

Installing the control panel consists of the following 

general steps: 

 

• 

Connecting the main power to the control 
panel  

• 

Connecting the activating device 

• 

Connecting the operator to the control panel 

• 

Checking the direction of the motor's rotation 

• 

Connecting other devices to the control panel 

• 

Set operating modes 

 

 

C

ONNECT

 

THE

 M

AIN

 P

OWER

 S

UPPLY

 

 

WARNING! 

Turn the main power off before you 

make any electrical connections or before 

programming. 

 

Wire the main power supply to control panel terminals 

in block J3 (see Figures 1 and 2). The installer is 

responsible for insuring that a separate, grounded 

circuit protected by a circuit breaker is between the 

control panel and the main power supply. All wiring 

should conform to applicable electrical codes, and all 

wiring and fittings should be weatherproof and/or 

suitable for burial. 

 

Connect the ground to the grounding terminal in block 

J3 and connect the power wires to the terminals labeled 

N (neutral) and L (line). 

 

N

OTE

:  

For a 230V system, a neutral is not 

needed.  Connect one 115V line to the L (Line) 

and a second 115V line to the N (Neutral).   

 

Page 2 

November, 2003 

455 D Control Panel Installation Instructions 

Summary of Contents for 455 D

Page 1: ...es 10 Learning of Normal Times 10 Learning Times with Gatecoder 10 Automated System Test 11 Logic Tables of 455 D Control Panel 12 Safety in Gate Design 14 Maintenance 14 Limited Warranty 16 T H E 4 5...

Page 2: ...reaker switch and for making sure that the entire gate system meets all applicable electrical codes The installer should refer to the installation manual for a given operator for more information NOTE...

Page 3: ...e each leg of the capacitor supplied to terminals 2 3 Note If you want to delay the closing of one gate leaf in a two leaf gate design be sure to connect its operator to Motor 1 In order to wire motor...

Page 4: ...pplying power to accessories through terminals 17 or 18 and 14 or 15 or 16 on terminal block J1 In most cases this source can be used to power 24 VDC accessories NOTE The 455 D control panel allows a...

Page 5: ...OP_B Partial Opening should illuminate only when an activating signal is sent for 2 and 1 gate leaves respectively STOP should be illuminated except when the stop button is pressed FSWOP and FSWCL sh...

Page 6: ...is set at less than the leaf delay time the delayed leaf closes at the end of the closing time Page 6 November 2003 455 D Control Panel Installation Instructions opening and closing respectively are...

Page 7: ...ls f or opening 1 2 1 2 3 4 5 17 13 19 14 17 Additional Reversing Devices TX RX 1 2 1 2 3 4 5 19 17 12 19 17 Additional Reversing Devices TX RX 1 2 19 12 17 15 Additional Reversing Devices 8 7 Safety...

Page 8: ...and if you release it the value that can be modified with keys and When you reach the last function press the F key to exit the program and the display resumes showing the status of the inputs The tab...

Page 9: ...ed the output functions as a standard indicator light lighted at opening and pause flashing at closing and off when gate closed Different figures correspond to timed activation of the output which can...

Page 10: ...automatically when the opening positive stop is reached and the display stops flashing The procedure has ended and the gate is ready to operate using default slow down automatically set by the control...

Page 11: ...top the operator will automatically shut off An open command must be given to start closing gate operator 2 When gate operator 2 reaches the position that you want it to slow down an open command must...

Page 12: ...t Closed Opens both leaves and closes them after pause time Opens single leaf connected to Motor 1 and closes it after pause time No effect No effect No effect Off Opening Closes both leaves Closes le...

Page 13: ...or 1 No effect opening is inhibited No effect opening is inhibited No effect opening is inhibited Off Opening Stops Stops Stops Stops gate closes when reversing device no longer trig gered No effect O...

Page 14: ...rians should not use a vehicular gate system Prevent such inappropriate use by installing separate gates for pedestrians The operating controls for an automatic gate must be secured to prevent the una...

Page 15: ...Page 15 November 2003 455 D Control Panel Installation Instructions This page is left blank intentionally...

Page 16: ...subject to misuse negligence or accident or has not been operated in accordance with FAAC International Inc s or FAAC S p A s instructions or has been operated under conditions more severe than or oth...

Reviews: