2.
Connect electrical mains cables to the rear of the x-ray high-voltage controller, the x-ray system
controller, the pump box and the water chiller. Mains cables are not included except when a UPS was
purchased together with the system. Verify that all electrical mains cables connected to each sub-
assembly are connected to a residual-current circuit breaker and that the supply voltage is within the
specifications in Table 4-4.
Sub-assembly unit
Mains supply
X-ray system controller: 208-240 VAC, 50/60 Hz, 0.5 kW
208-240 V 2
~
, 50/60 Hz, 0.5 kW
X-ray high-voltage controller: 208-240 VAC, 50/60 Hz, 0.5 kW
208-240 V 2
~
, 50/60 Hz, 0.5 kW
High-voltage controller:
(MetalJet D2+ 160 kV)
208-240 VAC, 50/60 Hz, 0.8 kW
208-240 V 2
~
, 50/60 Hz, 0.8 kW
Pump box: 208-240 VAC, 50/60 Hz, 2 kW
208-240 V 2
~
, 50/60 Hz, 2 kW
Water chiller: See water chiller operating manual
Table 4-4.
Mains supply specifications.
WARNING
Residual current devices must be used
For safety reasons, the power cables must be plugged into sockets equipped with residual current devices.
NOTE
Disconnecting device must be used in final installation
The installation must incorporate a disconnecting device, which disconnects all current-carrying conductors.