Place concrete up to the ground level. The lower plate must be sealed at least 4 cm in the concrete.
The five available threaded rods must have a height of 80 mm from the ground.
Step 5:
-
Allow it to dry for the time required.
Note:
1.
If necessary, level the terminal support plate (raw aluminium) using the bottom nuts.
3.3.3
Preparing and installing the charger WITHOUT Auxiliary power cabinet
(APC):
To be movable and easily installed, some mechanical parts can be removed prior to installation:
Step 1:
-
Remove the front bumper by unscrewing the screws from the inside and underside of the door.