Parallel buffer connection
Buffer storage tank
8.4
Parallel buffer connection
Parallel buffer connection with internal Tichelmann
The basic principle of the internal Tichelmann is diagonal flow; Two buffers are connected together at the top and
bottom (= parallel connection). For output up to 90 kW, a connection with DN 32 (ETA buffer connection set) is
sufficient, for 30 kW use at least R1" or 28 mm copper. On one tank, the boiler outlet is connected at the top; on
the other the boiler return is connected at the bottom. Return lines with greatly differing temperatures should be fed
into the buffer storage tank separately. To minimize pipe circulation losses, it is helpful to make the connections with
downward siphon loops.
With hot water tank
1
Boiler flow, heating circuits, hot water tank, oil/gas boiler flow
2
Oil/gas boiler return
3
Hot water tank return, high-temperature circuit return
4
Boiler, low-temperature circuit return
5
Temperature sensor [Sensor 1 (upper)]
6
Temperature sensor [Sensor 2]
7
Temperature sensor [Sensor 3]
Summary of Contents for 13180 LP-D
Page 1: ...2020 04 21 EN 0000000475 V 006 5402 00 939091 002 Pellet boiler ePE K 180 240 kW Installation ...
Page 33: ...Buffer storage tank Connection between multiple buffer storage tanks 33 ...
Page 55: ...Installation Network connection 55 ...
Page 61: ...Electrical connections Overview of circuit boards 61 ...
Page 65: ...Electrical connections Circuit board HA C5 65 ...
Page 85: ......
Page 86: ...www eta co at ...
Page 87: ......
Page 88: ...www eta co at www eta co at downloads DOWNLOAD ...