Instruction manual for installation and operation of automatic pellet burner “ERATO GP20+”
(Version :
02.02.2010 10:36
)
p.
15/50
4.
Installation of automatic pellet burner
Requirements and recommendations.
4.1.
Some basic requirements for correct installation of automatic pellet
burner “ERATO GP20+” are
•
The burner should be positioned in order to guarantee comfort
maintenance and easy access for cleaning procedures;
•
The main unit of the burner should be installed on a unit (a boiler, heat
consumer, etc.), which has the appropriate thermal capacity, at least equal
that of the burner and should provide easy access for burner’s grate
cleaning and ash removal;
•
It is strongly forbidden to install the burner in dwellings, including
corridors;
•
The installation process of the burner, its attachment and connection of
the power supply and control should be performed by authorized personal
only;
•
Installation and maintenance of the burner is performed by specialized
trained personal of authorized companies;
•
Connection of the burner to the power supply and the control board
should be performed by authorized technician only;
•
Before starting the burner, the heat consumer unit (at which the burner is
attached) should be thoroughly checked in order to guarantee safe
operation of the system;
•
The maintenance of the burner should be performed by adult person, who
is familiar with the safety procedures and the user manual of the
appliance;
4.2.
Installation of the burner
The installation process of the burner should be based on authorized
project, which is governs the requirements of acting norms and
recommendations.
•
In case that the heat consumer unit is solid fuel hot water boiler, that the
requirements are depicted in norm EN 303-5/2000 - „„
Heating boilers.
Part 5 : Heating boilers for solid fuels, hand and automatically fired,
nominal heat output of up to 300 kW. Terminology, requirements, testing
and marking
”;