3.
Connect the supplied M12 4 metre
cables (CB001026) into each of the
pressure sensors.
Cable tie the main head pressure
sensor cable to the flexible hydraulic
hoses connected to the main lift
cylinder. Make sure the cable isn't
pinched or stretched when the boom
is raised or lowered.
Run the remainder of the cable
towards the rear of the cabin and
cable tie with the other cables
during External Cable Completion on
page 30.
Table 5: Main Lift Cylinder – Boom Suspension Option
Angle the tee connections to ensure the hydraulic connections
and pressure sensor do not hit the boom when the boom is
lowered
For further details on running the pressure sensor cables
refer to the Installation Index on page 7
18 of 53
Summary of Contents for Gen-3 LMS
Page 5: ...Appendix B Reattach Ferrites 51 Indexes and Tables 52 VER 1805241756 5 of 53...
Page 9: ...Illustration 1 Machine Boom VER 1805241756 9 of 53...
Page 10: ...Illustration 2 Machine Chassis VER 1805241756 10 of 53...
Page 43: ...Complete the system checklist once installation has been completed VER 1805241756 43 of 53...