20
RAK133_ENG / © Ensto 2019
11. Installation / Commissioning Checklist
Introduction
This checklist is a guidance for ensuring both mechanical and electrical installation as well as
commissioning of the Wallbox.
Checking the Installation
Go through the visual, mechanical and electrical installation when the charger is un-
powered.
CATEGORY
X ITEM
Overall look
Ordered material has been received.
Protective plastic wrapping have been removed.
No scratches or damages may be seen.
Mechanical
installation
Charging station is fixed properly on installation site.
Electrical
installation
Charging station’s power supply capacity meets electrical planning (cable
size, MCB…).
Review local electrical design plan.
Gently push the charging station with a hand to create vibration to en-
sure no bad contact / connection exist (wire or PCB).
Check tightness of the PE-cable screw.
Power supply cables (L1, L2, L3, N and PE) are properly connected.
Insulation of power supply cables is intact (L1, L2, L3, N and PE).
Voltage between PE and N is less than 10 V.
PE conductor resistance is less than 3 Ω.
Operational
check
All the LED states / colors (green, blue, red) and the RFID reader are
functioning.
Create fail and charge with a RFID tag. Red at bootup, green at idle and
blue while charging.
Available electricity at the sockets. All the contacts (L1, L2, L3) must be
tested.
Use a Mode 3 tester.
Verify that when charging point’s LED is green, there is no power at the
socket contact (L1, L2, L3, N).
Test the functioning of Mode 3 (from green to blue).
Use a Mode 3 tester.
Test the function of the RCD / MCB.
Ready for
use
Correct SW is in use.
Correct operating mode is in use:
•
Standalone
•
Online