Chapter 4 Operation Instructions 35
SmartCabinet Integrated Solution User Manual
Chapter 4 Operation Instructions
This chapter introduces the operation instructions of SmartCabinet, including check before startup, and procedures of
power on and power off.
4.1 Check Before Startup
Check the following before startup of SmartCabinet:
1. Check whether the AC pipe system is connected correctly and firmly, and there is no leakage.
2. Check and confirm that the power distribution mode of UPS and PMU, connections of the power cables and the
signal cables are correct, and that there is no short circuit.
3. Check that the installation and cable connection of the batteries are correct, and that the positive pole and negative
pole of the battery are correct.
4. Measure and check that the voltage and frequency of the mains are normal.
5. Check and confirm that all of the communication cables are connected correctly and firmly.
6. Check and confirm that the remained unoccupied U height space is covered by the dummy plate.
Warning
1. Before startup of the SmartCabinet, ensure that the maintenance bypass air breaker on the MSC-PMU is off and locked by a
metal latch.
2. Before startup, ensure that the indicator of the SPD module is green.
4.2 Startup
The startup flow chart of SmartCabinet is shown in Figure 4-1.
Closing
external input
power switch
Closing the air breakers of
total input on the PMU,
SPD, UPS output, PDU,
lighting & LCD in turn
Start up user
devices
Wait for LCD
startup, log in the
SmartCabinet
monitoring system
UPS startup
Closing input
air breaker
downstream
the UPS
Figure 4-1 Startup flow chart
The startup procedures are as follows:
1. Close the external input power switch.
2. Close the input air breaker downstream the UPS.
3. Close the main input air breaker on the MSC-PMU, SPD module air breaker, UPS input air breaker, AC input
power air breaker, UPS output air breaker, lighting & LCD air breaker from left to right in turn, as shown in Figure 4-2.