14 Chapter 2 Single UPS Installation And Commissioning
Liebert
®
ITA 5kVA And 6kVA UPS User Manual
Guide rail screw (4 pcs)
Guide rail
Guide rail holder
Square hole
Figure 2-16 Installing the guide rail
Note
1. The guide rail holder must be close to the front of the rack.
2. Any end of one guide rail has six installation holes (see Figure 2-9), do not use the two installation holes in the middle when
fixing the guide rail. It is recommended to use the top and bottom installation hole (from top to bottom, installation hole 1 and
installation hole 6).
The guide rail installation is finished, as shown in Figure 2-12.
Figure 2-17 Guide rail installation complete
4. Place the UPS on the guide rails in the rack, and push it completely into the rack. Use four panel screws (M4 × 16)
to fix the UPS in the rack through the installation hole 2 of the brackets, as shown in Figure 2-13.
UPS
Rack
Installation hole 2 (4 pcs)
Screw
(4 pcs)
Figure 2-18 Installing the UPS
Installation procedures for UPS with battery modules
The installation method of the battery module is the same as that of the UPS. Repeat the installation procedures of the
UPS to install and fix the battery modules and the UPS in the rack one by one, as shown in Figure 2-14.
Because the battery module is heavy, you should pay attention to the following items in installation:
Install the battery modules first, start the installation from the bottom, and then place the UPS onto the top, as
shown in Figure 2-14.
It is prohibited to move the UPS and battery modules through the brackets.
Two persons or more are required for the installation.