The AMS Asset Monitor is available with cable inlets with NPT thread.
•
For hazardous location installation, use cable glands and screw plugs with an
appropriate approval.
Procedure
1. Remove all red dust caps.
Press the caps out from the inside or use a pair of pliers to pull them out.
2. Screw the required cable glands into the cable inlets.
Ensure proper sealing of the cable glands to keep the IP protection of the AMS Asset
Monitor. See documentation of the used cable glands for details.
3. Close the remaining cable inlets with screw plugs.
Ensure proper sealing of the cable inlets to keep the IP protection of the AMS Asset
Monitor. See documentation of the used screw plugs for details.
4. Continue with wiring and cable installation.
4.10
Grounding
Note
The grounding connections, described in this section, are examples. Adapt these examples
to the installation situation on-site. Observe local regulations regarding grounding and
installation of electrical equipment. The transition resistance between housing and
protective ground must be <100 m
Ω
measured at 40 A. The connection cable must be
colored green or green/yellow.
The AMS Asset Monitor has a grounding terminal at the bottom. The grounding terminals
for the shields of the field wiring cables and the two additional internal grounding
terminals in the lower left and right corner are internally connected to this grounding
terminal.
A ground connection between the housing of the AMS Asset Monitor and protective
ground is at least required if field signals with up to 250 V AC are connected. The
KL4502X1-MA1 CHARM Relay Output Terminal Block may have hazardous live voltages on
its output terminals. This terminal block is capable to switch field power of up to 250 V AC.
The minimum required grounding connection is a connection between the labeled
internal grounding terminal and protective ground.
Installing AMS Asset Monitor hardware
Installation Guide
April 2020
MHM-97923-PBF
38
MHM-97923-PBF, Rev. 1.0
Summary of Contents for AMS
Page 8: ...Contents Installation Guide April 2020 MHM 97923 PBF viii MHM 97923 PBF Rev 1 0 ...
Page 14: ...General Installation Guide April 2020 MHM 97923 PBF 14 MHM 97923 PBF Rev 1 0 ...
Page 72: ...Removing CHARMs hardware Installation Guide April 2020 MHM 97923 PBF 72 MHM 97923 PBF Rev 1 0 ...
Page 86: ...Technical data Installation Guide April 2020 MHM 97923 PBF 86 MHM 97923 PBF Rev 1 0 ...
Page 88: ...Certificates Installation Guide April 2020 MHM 97923 PBF 88 MHM 97923 PBF Rev 1 0 ...
Page 89: ...Installation Guide MHM 97923 PBF April 2020 MHM 97923 PBF Rev 1 0 89 ...
Page 90: ...Installation Guide April 2020 MHM 97923 PBF 90 MHM 97923 PBF Rev 1 0 ...
Page 91: ...Installation Guide MHM 97923 PBF April 2020 MHM 97923 PBF Rev 1 0 91 ...