Installing the Hardware
Installing a cluster
Task 1: Unpack and
set up the cabinet
Follow the steps in the EMC
40U-C Cabinet Unpacking and Setup Guide
, which
accompanies each VPLEX cabinet (and is available on Powerlink).
Task 2: Check the
components
To confirm that no components loosened during shipping:
1. From the rear of the cabinet, push each director and the I/O module carrier
(shown in
) inward, to verify that these components are fully seated.
Figure 5
Directors and I/O module carrier
If any of these components is not fully seated, loosen the orange captive screws,
push the component firmly into the backplane, and retighten the thumbscrews.
2. Confirm that all I/O modules are fully seated.
3. Confirm that all thumbscrews are finger-tight.
4. Confirm that all cables in the cabinet (except AC cables to site power) are securely
connected, and that the wire bail on each SPS power cable, as well as (if present)
each UPS and Fibre Channel switch power cable, is secure.
The bail on each SPS and UPS cable must be clamped onto the plug’s plastic
molding, and the bail on each Fibre Channel switch must be clamped onto the
cable itself, as shown in
Figure 6
Power cable wire bails
If any cable has become disconnected, reconnect it as identified by the labels on
the cable and cabinet, as well as
of this guide.
Director “n” B
Director “n” A
I/O mod
u
le carrier
Zep-041
SYM-002500z
SPS and UPS
:
The wire cable bail is inserted into
the middle of the pl
u
g’s plastic molding.
Fibre Channel switch
:
The wire cable bail is against
the end of the pl
u
g’s plastic molding.
Summary of Contents for VPLEX
Page 8: ...EMC VPLEX with GeoSynchrony 4 1 Installation and Setup Guide 8 Tables...
Page 20: ...EMC VPLEX with GeoSynchrony 4 1 Installation and Setup Guide 20 Introduction...
Page 76: ...EMC VPLEX with GeoSynchrony 4 1 Installation and Setup Guide 76 Setting up VPLEX...
Page 92: ...EMC VPLEX with GeoSynchrony 4 1 Installation and Setup Guide 92 Reference...
Page 94: ...EMC VPLEX with GeoSynchrony 4 1 Installation and Setup Guide 94 Index...