BOILER SET-UP
2. BOILER SET-UP
A. GENERAL
1. Peak boilers are intended for installation in an area with a
floor drain or in a suitable drain pan. Do not install any boiler
where leaks or relief valve discharge will cause property
damage.
2. The Peak boiler is not intended to support external piping. All
venting and other piping should be supported independently
of the boiler.
3. Install the boiler level to prevent condensate from backing up
inside the boiler.
3. Peak boilers are wall mounted.
B. UNPACKING THE UNIT
1. Items included inside of the boiler cabinet:
a. Two vent adapters
b. Miscellaneous parts kit
2. Remove external foam packaging and remove the front
panel from the unit. The unit can be easily lifted out of the
carton by gripping the bottom front edge of the base panel
and the inside of the front edge of the top panel.
3. With the boiler flat on the back panel, remove the right side
panel to access the vent adapters and miscellaneous kit.
Remove these components.
4.
Remove the internal packaging block behind the
gas valve.
5. The boiler can now be placed upright on a flat stable
surface for further pre-installation work.
C. MOUNTING
1. A wall mounting bracket kit (5636) is included for wall
mounting these boiler sizes.
2. Mount the bracket level on the wall using 5/16" lag bolts.
Be sure the lag bolts are fully supported by wall studs or
adequate wall structure.
CAUTION
This boiler must be installed level to prevent
condensate from backing up inside the boiler.
3. The mounting bracket has (4) holes on 16" centers as shown
in Figure 2.1. This is intended to give installers the ability to
mount the bracket on two wall studs spaced at this interval.
If existing wall studs are spaced differently or if the desired
location is not in line with the wall studs additional support
is required.
4. Install the two ½"-13 by 4" bolts supplied with the boiler
into the weld nuts in the base of the unit. The depth that
these are threaded into the base can be adjusted to assure
the proper level of the boiler. Adjust the bolts until the unit
is tilted slightly off level to the rear to aid in condensate
draining.
5. Be sure that the wall provides adequate support for the
boiler.
6. Be sure to adequately support the boiler while installing
external piping or other connections.
7. Be sure that condensate piping is routed to a suitable drain
or condensate pump.
WARNING
WARNING
The wall mounting bracket is designed to support the
boiler. External piping for water, venting, air intake
and fuel supply is to be supported separately.
Make sure the boiler wall bracket is adequately
supported. Do not install this bracket on dry wall
unless adequately supported by wall studs.
Figure 2.1: Wall Mounting Bracket
Summary of Contents for Peak-40
Page 22: ...22 WATER PIPING AND CONTROLS Figure 4 6 Recommended Central Heat Piping ...
Page 24: ...24 WATER PIPING AND CONTROLS Figure 4 8 Recommended Domestic Hot Water Piping ...
Page 33: ...33 ELECTRICAL CONNECTIONS Figure 7 4 Wiring Schematic and Connection ...
Page 47: ...47 START UP PROCEDURE E LIGHTING OPERATING PROCEDURES ...
Page 59: ...59 THIS PAGE INTENTIONALLY LEFT BLANK ...
Page 62: ...62 REPAIR PARTS Figure 13 2 Peak 40 LP Combustion Components ...
Page 64: ...64 REPAIR PARTS Figure 13 3 Peak 40 NG Combustion Components ...
Page 66: ...66 REPAIR PARTS Figure 13 4 CHB Parts Detail ...
Page 68: ...315 Oser Avenue Hauppauge NY 11788 Tel 631 694 1800 Fax 631 694 1832 www embassyind com ...