Start-up
Inspection before commissioning
Autotest of control unit
LOADING
0%
100%
UNIT DEPROGRAMMED
Air Fuel oil
SAFETY UNIT TEST
UNIT DEPROGRAMMED
Inspection before commissioning
Before starting the burner, carry out the
following checks and/or inspections:
- The operating instructions of the heat
generator manufacturer.
- Adjusting the following devices:
- temperature regulator,
- pressure regulator,
- limiter,
- safety pressure switch.
- Opening the chimney and supplying
sufficient cold air.
Self-testing of the unit
Switch on the burner. The ignition control unit runs a self-test. If the control unit has
not yet been programmed, the display will then show “UNIT DEPROGRAMMED”
Self-testing of unit and of air and gas stepper motors.
The displays loads the values held in the burner control unit.
The control unit has not yet been programmed.
en