Manual
Next, place the muffle articulated drying device on stage 4 Pic-10.
With everything ready we can start the burn by activating the S/S
(Start / Stop) key.
S/S
12-4)
The muffle articulated system for drying the piece entry and exit has 4
stopping stages (rest) that should be manually moved by the operator. An
adjustable inner clock will help you signal the time intermissions between the
TEMPERATURA - T1
In our example the piece will be drying for 5 minutes while
it keeps the temperature at T1=620ºC. The display will
show a message every time the alarm sounds, warning
the operator who should take the muffle articulated to the
next stage.
FECHA / DESCE
12-5)
The message “dE-4” (Stage-4) PIC-10 is the higher
articulated position, next we will have “dE-3” (Stage-3)
PIC-9, put it down to a lower position and then “dE-2”
(Stage-2) PIC-8, put it down once more “dE-1” (Stage-1)
PIC-7 and finally “FECH” (Burn start stage) PIC-6. At this moment, the operator
should press down the muffle puller to promote the chamber sealing and then start
with the vacuum suction.
12-6)
At this point, the furnace comes from Baseline T1 to
ramp T2 with heating speed at 55ºC/min until it reaches
T2=900ºC, in which it should be kept on burning for 1 min
PAT-2=(01.00) with vaccum for 30 sec. VAC-2=(00.30).
TEMPERATURA = T2
LIBERA VÁCUO
12-7)
At the end of the vacuum time, the pump will be off
and the display will show a message while it waits for the
AIR return to the chamber. Next the piece exit time will
start counting and it will be signalized by an alarm and a
message.