ELECTRICAL ENTRY
The electrical supply to the boiler must be 230v/50hz, fused at 5 amps. Connection of the appliance and any
system controls, to the mains supply, must be a common isolator and must be fused at 5A maximum.
This must be fixed wired to a double pole-isolating switch that has a maximum contact separation of 2mm in
both poles. The isolator should be clearly marked showing its purpose, and preferably positioned close to the
boiler.
COMMISSIONING & SERVICING INSTRUCTIONS
A competent service engineer OFTEC registered should be appointed on an annual basis.
Isolate Power to the boiler
De-pressurise heating system and check expansion vessel pre-charge is the same as the cold fill
pressure, of the heating system. Expansion vessel pre-charge must not exceed 1.5 bar.
Remove inspection door, burner and baffle assembly
Brush down the inside of the heat exchanger and vacuum out debris
Clean baffle assembly
Pull out inserts from stainless steel heat exchanger and clean before replacing.
Ensure stainless steel heat exchanger is thoroughly cleaned.
Empty and clean condensing trap
Inspect and clean burner assembly, and replace with new nozzle (see burner manual)
Renew any insulation e.g. inspection door or inside base of heat exchanger
Reassemble baffles and replace inspection door.
Replace paper oil filters
Turn electrical supply to the boiler to ON.