NOTE
Always test the REPO function before applying your critical load to avoid accidental load loss.
UPS 6 REPO Terminals
+ Polarity
– Polarity
2
1
Normally-Open
+ Polarity
– Polarity
2
1
Normally-Closed
UPS 4 REPO Terminals
+ Polarity
– Polarity
2
1
Normally-Open
+ Polarity
– Polarity
2
1
Normally-Closed
UPS 5 REPO Terminals
+ Polarity
– Polarity
2
1
Normally-Open
+ Polarity
– Polarity
2
1
Normally-Closed
UPS 2 REPO Terminals
+ Polarity
– Polarity
2
1
Normally-Open
+ Polarity
– Polarity
2
1
Normally-Closed
UPS 3 REPO Terminals
+ Polarity
– Polarity
2
1
Normally-Open
+ Polarity
– Polarity
2
1
Normally-Closed
UPS 1 REPO Terminals
+ Polarity
– Polarity
2
1
Normally-Open
+ Polarity
– Polarity
2
1
Normally-Closed
REPO Switch
(Normally-Open)
Factory-Installed Jumper Wire
(do not remove)
Figure 53. Normally-Open REPO Switch Wiring in a Parallel System
Summary of Contents for Powerware Series
Page 1: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 2: ......
Page 3: ...Powerware Series Eaton BladeUPS 12 kVA User s Guide ...
Page 84: ...OPERATION EATON BladeUPS 12 kVA User s Guide S 164201649 Rev 4www eaton com powerquality 76 ...
Page 119: ......
Page 120: ... 1642016494 164201649 4 ...