4.3
MBM Installation
The method used to install the MBM depends on the type of installation. The MBM
can be installed as a
line-up-and-match
or
standalone
system. The term
line-up-and-match
refers to cabinets that are physically attached to the UPS, and the
wiring between them is internal. The term
standalone
refers to cabinets that are not
physically attached to the UPS, and are wired with external customer-supplied conduit
and wiring.
S
To install a
line-up-and-match
MBM, proceed to paragraph 4.3.1.
S
To install a
standalone
MBM, proceed to paragraph 4.3.4.
NOTE
If a Field Installed UPM (FI-UPM) is installed or will be installed in the future, the MBM must be
installed in a standalone configuration.