System assembly
28
Power Xpert
®
UX with W-VACi
circuit breaker 6063308 G01 01 14 July 2011 www.eaton.com
3.2.3 Transport in the operating area
The installation can be moved in the operating area by
means of all suitable aids. This can vary from solid bars,
lifting trolleys, inside cranes or forklift trucks.
Solid bars
1. Lift the Power Xpert
®
UX on one side and put a solid
bar under the equipment.
2. Repeat this until a bar is present under each section.
3. Put some bars in front of the transport direction and
push the Power Xpert
®
towards its final location.
4. Remove the bars in reverse order.
CAUTION
Make sure, under each section a solid bar is always
present. This is to prevent sagging.
Lifting trolleys
1. Lift the Power Xpert
®
UX on one side and put a lifting
trolley under the installation end.
2. Support the installation adequately to prevent rolling
away
3. Lift the Power Xpert
®
UX on the other side and put a
lifting trolley under the installation end
4. Carefully push the Power Xpert
®
UX towards its final
location.
5. Remove the lifting trolleys in reverse order.
Inside cranes
Transport by indoor cranes is done in the same way as
outside transport. Please refer to the applicable paragraph
above.
Forklift trucks
Transport by forklift trucks is done in the same way as
outside transport. Please refer to the applicable paragraph
above.
3.3
System assembly
3.3.1
Foundation on site
The switchroom needs to provide a suitable foundation in
order to mount the switchgear assembly. The dimension
of foundation is based on the depth and width of the
switchgear. There are many types of switchgear in the UX
series and the dimensions of the foundation are different.
For detailed foundation, please go to par. 9.2 of Appendix.
3.3.2
Unpacking the delivery
Dispose of the packing material in an environmentally
sound manner. It is essential to adequately pack the
products so as to avoid damage. All packing materials are
inoffensive to the environment and they can be re-used.
If any wood is used, it has not been treated chemically.
Foils are from polyethylene (PE). CFC-free polystyrene
foam is used for padding. These plastics are pure
hydrocarbon compounds, so they can be recycled. If
incinerated, there will be no emissions that are offensive
to the environment.
REMARK
By using and reusing packing materials, we can
save on raw materials. This again reduces the
amount of waste.
Procedure
1. As required, remove the packaging materials from the
equipment.
2. Dispose the packaging materials in an environmental
friendly manner.
3.3.3
Inspection of the floor
NOTE
The maximum difference in height with reference to
width and length of the installation shall not exceed 4
mm.
1. Prior to the installation, make sure the floor is smooth
and level.
2. Find the highest point in the installation area.
Installation of the sections should start from this point.
Differences in height must be eliminated with the use
of shims.
3. Check the location of the recesses with reference to
the approved floor plan, which is part of the
information package to which this manual belongs.
4. Check the location of the cable trench / cable cellar
with reference to the floor plan.
5. If any cables come out of the floor, make sure they
are electrically insulated.
6. Put the cables downwards or into the cable
cellar/trench in such a way that the Power Xpert
®
switchgear can be installed on top.