Eaton PDI WaveStar Infinity 2 Monitoring System Setup and Operation Manual P-164001106—Rev 01
65
Table 6. Replacing a Failed Panelboard CT – Procedure (Continued)
10.
Clip a
split-core CT
over the panelboard circuit
wire for
CT2
.
11.
Connect the split-core CT monitoring cable to the
CT Fix position on the CT Strip that corresponds to
the screen CT Fix position. (1=Top, 2=Middle, 3=
Bottom)
NOTE:
On 84-pole panelboards, there are four (4)
sensor strips and lower strips are inverted
compared to upper strips. CT Fix positions are as
follows:
•
Upper strips (CT Fix 1=Top, 2=Middle, 3=
Bottom)
Lower strips (CT Fix 1=Bottom, 2=Middle, 3=Top)
CT Fix 1
CT Fix 2