Installing Battery Cabinets
3-7
EATON
Powerware
®
9390 Integrated Battery Cabinet (Models IBC-S and IBC-L) Installation Manual
S
164201536 Rev D
www.eaton.com/powerquality
12.
Align the holes in the other end of the bracket with the holes in the bottom
right-hand side of the battery cabinet (see Figure 3‐4). Secure the bracket with
hardware from the field kit.
13.
Route the ground wire (from the field kit) from the ground stud in the battery
cabinet, under the lower right‐hand battery tray, through the access hole in the
side panel of the UPS, and attach to the ground stud in the UPS cabinet (see
Figure 3‐4). Hardware is provided on each ground stud.
14.
If installing additional battery cabinets, repeat Steps 2 through 13 to join each
additional battery cabinet; otherwise, proceed to Step 15.
15.
If not already installed, mount the hanger brackets to the top left side of the last
battery cabinet using M4 screws (see Figure 3‐5).
16.
If not already installed, hang the side panel on the hanger brackets and align with
the front and rear of the battery cabinet.
17.
If not already secured, secure the side panel at the bottom using M4 hex-head
screws previously removed.
18.
Hanger Bracket Location
(Secured with Screws)
Cabinet-to-Cabinet
Cable Access Area
(Each Side)
Figure 3‐5. IBC-S Hanger Brackets