7. Commissioning
7.1 Unit switch-on
Professional and qualified personnel must be expert in the field, and are therefore responsible for
commissioning the system in accordance with the manufacturer’s instructions and local legislation.
Before switching on the EV charger, check the effectiveness of the safety measure(s) of the system in
accordance with the local regulations.
Electrical systems or devices must be checked by the installer of the system before commissioning and
switching on the unit.
Before switching on the product, please do the following:
Step 1.
Check that the equipment is correctly fixed to the wall or the floor-mount pedestal in accordance
with local regulations.
Step 2.
Check that the electrical connections have been made correctly in accordance with local
regulations.
Step 3.
Check that the EARTH connection (MANDATORY) has been made correctly in accordance with
local regulations.
Step 4.
Perform checks on the continuity of the connections of the protective conductor, insulation
resistance, RCD triggering current, triggering time, etc., in accordance with local regulations.
Step 5.
Verify that the front door is closed and secured with the fixing screws.
If the checks listed above were successful, proceed as follows:
Step 1.
Close the main AC GRID circuit breakers.
Step 2.
Wait for the display to turn on.
Step 3.
Visit the link or scan the QR code to fill out the installation checklist form at:
https://content.eaton.com/en-gb-installation-checklist-ev-chargers
7.2 Online station
The Green Motion DC 22 EV charger uses a software management system, Eaton Charging network manager which
controls the EV charging stations network. Refer to the Eaton Charging network manager user manual, available on
www.eaton.com, for further details.
The Green Motion DC 22 DC EV charger communicates with the remote database via the cloud infrastructure.
Figure 24. QR code for installation
checklist online form
Figure 25. Simplified illustration of Green Motion DC 22 EV charger communication
Tag
Description
1
Green Motion DC 22
EV charger
2
Cloud
3
Remote database
1
2
3
RFID