background image

Utilizing a voltmetre, measure phase-to-phase and
phase-to-neutral voltages across the Emergency
Bypass Line Terminal to insure Emergency voltage is
correct. If necessary, make adjustments to the
voltage regulator on the generator according to the
manufacturer’s recommendations to correct any
observed voltage deviations.
The following enclosure mounted status indicator
lights should be lit.

1.

Emergency Bypass Energized

2. Transfer Switch Isolated
3. Normal Source Available
4. Emergency Source Available
5. Load Energized
6. Normal Position Energized

ATS FUNCTIONAL TEST WITHOUT LOAD
TRANSFER

While the ATSBI Switch is in either Bypass position,
the ATS is isolated from the power circuits of both
sources. The ATS Logic Panel is, however, still
connected, via a test cable harness, to control
power enabling complete electrical and mechanical
testing of the ATS.

ENERGIZING ATS

Following the operational instruction label on the
enclosure front, proceed to energize the ATS by
opening the appropriate closed Bypass Switch and
placing the isolation Switch in the “ON” position.
Load circuits will now be connected to the ATS
power contacts.

The following enclosure mounted indicator lights will
be lit assuming availability of both sources.

1.

Normal Source Available

2. Emergency Source Available
3. Load Energized
4. Normal Position Energized

Once the ATS has been energized, the ATSBI
equipment is ready for standby service. Position the
Generator control selector switch to the auto start
position.

Additional functional load transfer tests may be
desirable including automatic engine start operation.

See ATS Controller Manual for additional testing and
troubleshooting information.

TRANSFER SWITCH REMOVAL

Cutler-Hammer Automatic Transfer Switches typically
do not require periodic maintenance or inspection
necessitating the removal of the ATS from service. If
removal is necessary, the following procedure
explains how to remoe the Automatic Transfer
Switch from service.

1.

Bypass and Isolate the Automatic Transfer 
Switch by carefully following operational 
instructions on previous pages. Verify that the 
“Transfer Switch Isolated” is lit.

THE BYPASS-ISOLATION SWITCH IS STILL
ENERGIZED. CONTACT WITH  ENERGIZED
COMPONENTS CAN CAUSE SEVERE PERSONAL
INJURY AND DEATH.

USE EXTREME CAUTION TO AVOID CONTACT
WITH THE BYPASS ISOLATION SWITCH.

2. Open enclosure doors(s) all the way and using a 

voltmeter verify ABSENCE of voltage on all line 
input terminals of both the Normal and 
Emergency ATS Switches.

3. Disconnect plugs interconnecting the ATS power

panel with the logic panel.

4. Disconnect interconnecting bus bars terminating

on the Normal and Emergency switches line 
input points (N1, N2, N3, E1, E2, E3 and N if 
supplied).

5. Disconnect wiring to terminals which isolate 

pilot circuits wired to the logic panel.

6. Remove bolts which hold the power panel to the

enclosure internal support brackets and lift the 
power panel carefully forward through the 
enclosure doors.

Effective July 2007 Supercedes I.L. 16913 dated February 1991

10

I.L. 16913A

DANGER

Summary of Contents for Cutler-Hammer BIHI

Page 1: ...IN INTERLOCKS AND SAFETY FEATURES INTENDED TO PROVIDE SAFE AND PROPER OPERATING SEQUENCES TO PROTECT PERSONNEL ASSOCIATED WITH THE INSTALLATION OPERATION AND MAINTENANCE OF THIS EQUIPMENT THE FOLLOWI...

Page 2: ...ontacting the factory for technical support A ratings nameplate will also be affixed to the switch identifying the withstand interrupting and closing ratings for which the unit is intended DO NOT APPL...

Page 3: ...ency bypass switches are provided to permit bypass to either power source but both bypass switches are interlocked with the isolation switch to positively prevent inadvertent paralleling of sources IN...

Page 4: ...Effective July 2007 3 I L 16913A Fig 2 Note For bottom entry add 14 to depth of unit...

Page 5: ...4 24 610 Single Phase Only DIMENSIONS INCHES MM BYPASS ISOLATION ATS 2 3 POLE DIMENSIONS INCHES MM BYPASS ISOLATION ATS 4 POLE Max Max Switch CSA Amps Volts Frame Bypass Frame A B C D E F G H I J 150...

Page 6: ...or ringing of the conductor strands Prepare stripped conductor termination end by cleaning with a wire brush If aluminum conductors are used apply an appropriate joint compound to the clean conductor...

Page 7: ...ition Connect the engine start wires to the RED terminal blocks marked 51A and 52A A contact closes between these terminal blocks when an engine start signal is provided by either the ATS or Bypass lo...

Page 8: ...Effective July 2007 7 Fig 3 I L 16913A...

Page 9: ...Effective July 2007 Supercedes I L 16913 dated February 1991 8 I L 16913A Fig 3...

Page 10: ...position if not already in normal This DOES NOT indicate a presence of voltage on the ATS power panel since the ATS logic panel senses on the line side of the Bypass switch Utilizing a voltmetre meas...

Page 11: ...osition the Generator control selector switch to the auto start position Additional functional load transfer tests may be desirable including automatic engine start operation See ATS Controller Manual...

Page 12: ...a downstream short circuit condition the ATS logic will engage the Transfer Mechanism to electrically reset the automatically opened switch If optional overcurrent protection option 16 17 or 37 is pro...

Page 13: ...us short circuit releases are replaced with conventional circuit breakers equipped with thermal elements in addition to magnetic releases to provide overload and short circuit protection to connected...

Page 14: ...ntenance agreements for our ATSBI product In most instances such maintenance agreements also extends warranty periods Contact your local Cutler Hammer Representative for more information on factory su...

Reviews: